2407-2407 1/2 E GATEWOOD ST 90031
Certificate Information: 2407-2407 1/2 E GATEWOOD ST 90031
- Application / Permit
- 21016-20000-15265
- Plan Check / Job No.
- B21VN07456
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT 32' X 24' (768 SF) A PORTION OF THE (E) DWELLING INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 5/4/2022
- Issuing Office
- Current Status
- CofO Issued on 11/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/18/2021 | JEFFREY TANGONAN |
| Corrections Issued | 6/19/2021 | JEFFREY TANGONAN |
| Applicant returned to address corrections | 4/7/2022 | JEFFREY TANGONAN |
| Plan Check Approved | 4/20/2022 | JEFFREY TANGONAN |
| Building Plans Picked Up | 4/20/2022 | APPLICANT |
| Issued | 5/4/2022 | APPLICANT |
| CofO in Progress | 10/26/2023 | THOMAS LOGRASSO |
| CofO Issued | 11/2/2023 | DEROLD HAUFF |
| Permit Finaled | 11/2/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/22/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 3/22/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/24/2022 | TREVOR QUAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Insulation | 8/8/2022 | Partial Approval | THOMAS LOGRASSO |
| Wood Frame | 8/8/2022 | Partial Approval | THOMAS LOGRASSO |
| Drywall Nailing | 9/2/2022 | Partial Approval | THOMAS LOGRASSO |
| Green Building Rough | 9/2/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Gas Test | 10/3/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 11/23/2022 | Partial Inspection | FREDDIE RIVERA |
| Drywall Nailing | 11/23/2022 | Partial Inspection | FREDDIE RIVERA |
| Final | 11/23/2022 | Partial Inspection | FREDDIE RIVERA |
| Gas Test | 11/23/2022 | Partial Inspection | FREDDIE RIVERA |
| Green Building Final | 11/23/2022 | Partial Inspection | FREDDIE RIVERA |
| Green Building Rough | 11/23/2022 | Partial Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 11/23/2022 | SGSOV Approved | FREDDIE RIVERA |
| Smoke Detectors | 11/23/2022 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 12/12/2022 | Conditional Approval | THOMAS LOGRASSO |
| Drywall Nailing | 12/12/2022 | Conditional Approval | THOMAS LOGRASSO |
| Green Building Final | 12/12/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Rough | 12/12/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 12/12/2022 | Corrections Issued | THOMAS LOGRASSO |
| Smoke Detectors | 12/12/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 12/28/2022 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 12/28/2022 | Approved | THOMAS LOGRASSO |
| Final | 12/28/2022 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 12/28/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Rough | 12/28/2022 | Approved | THOMAS LOGRASSO |
| Service/Power Release | 12/28/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 12/28/2022 | Approved | THOMAS LOGRASSO |
| Final | 2/27/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 2/27/2023 | Approved | THOMAS LOGRASSO |
| Service/Power Release | 2/27/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 10/25/2023 | OK to Issue CofO | THOMAS LOGRASSO |