17900 W TIARA ST 91316
Certificate Information: 17900 W TIARA ST 91316
- Application / Permit
- 21016-20000-15256
- Plan Check / Job No.
- B21VN07448
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND CONVERT THE (E) COVERED PATIO INTO (N) BEDROOM. IN EXISTING 1 STORY SINGE FMILY DEWLLING WITH ATTACHED GARAGE.
- Permit Issued
- Issued on 12/1/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/14/2021 | RARES BODEA |
| Corrections Issued | 6/14/2021 | RARES BODEA |
| Applicant returned to address corrections | 10/5/2021 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 11/14/2021 | ZAW HAN |
| Plan Check Approved | 11/23/2021 | ZAW HAN |
| Building Plans Picked Up | 11/24/2021 | APPLICANT |
| Issued | 12/1/2021 | APPLICANT |
| CofO in Progress | 6/20/2022 | VINCENT HANLEY |
| Permit Finaled | 8/27/2022 | MICHAEL SMITH |
| CofO Issued | 8/27/2022 | MICHAEL SMITH |
| Permit Finaled | 8/27/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 6/21/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 6/23/2021 | GABRIEL ROBLES |
| ZI | Cleared | 6/23/2021 | MIGUEL GAMBOA |
| Eng Process Fee Ord 176,300 | Cleared | 8/3/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 11/17/2021 | AMIR KASHFI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21500 WYANDOTTE ST 106 CANOGA PARK, CA 91303 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 5/6/2022 | Approved | SEAN HAUPT |
| Drywall Nailing | 5/6/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 5/6/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 5/6/2022 | Approved | SEAN HAUPT |
| Final | 5/6/2022 | Corrections Issued | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2022 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 5/6/2022 | Approved | SEAN HAUPT |
| Green Building Final | 5/6/2022 | Approved | SEAN HAUPT |
| Green Building Rough | 5/6/2022 | Approved | SEAN HAUPT |
| HVAC-Final | 5/6/2022 | Approved | SEAN HAUPT |
| HVAC-Rough | 5/6/2022 | Approved | SEAN HAUPT |
| Insulation | 5/6/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 5/6/2022 | Approved | SEAN HAUPT |
| PLUMBING-Final | 5/6/2022 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 5/6/2022 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 5/6/2022 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 5/6/2022 | Approved | SEAN HAUPT |
| Final | 6/17/2022 | OK to Issue CofO | VINCENT HANLEY |