10118 N OAK PARK AVE 91325
Certificate Information: 10118 N OAK PARK AVE 91325
- Application / Permit
- 21016-20000-15054
- Plan Check / Job No.
- B21VN07308
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL & REPLACE (E) 15' X 19' ATTACHED PATIO COVER ENCLOSURE. ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 10/18/2021
- Issuing Office
- Current Status
- Permit Finaled on 6/21/2022
Permit Application Status History
| Submitted | 6/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/11/2021 | HAYATO TSUCHIYA |
| Corrections Issued | 6/11/2021 | HAYATO TSUCHIYA |
| Plan Check Approved | 7/16/2021 | GURUNATH NESARAJAH |
| Issued | 10/18/2021 | APPLICANT |
| Building Plans Picked Up | 10/21/2021 | APPLICANT |
| Permit Finaled | 6/17/2022 | JAVIER RAMOS JR |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/22/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/25/2021 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 7/16/2021 | HAYATO TSUCHIYA |
Contact Information
| Contractor | Urbane Builders Inc; Lic. No.: 1046293-B | 8619 RESEDA BLVD STE 304B NORTHRIDGE, CA 91324 |
| Engineer | Ebrahimi,, Amirhosin; Lic. No.: C92049 | 8640 PETIT AVE APT 212 NORTHRIDGE, CA 91343 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/20/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 12/20/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| Excavation/Setback/Form/Re-Bar | 1/12/2022 | Approved | MARK JOHNSON |
| Footing/Foundation/Slab | 1/12/2022 | Approved | MARK JOHNSON |
| ELECTRICAL-Rough | 3/3/2022 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2022 | Partial Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 3/14/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 3/14/2022 | Approved | RAUL OLAGI |
| Insulation | 3/25/2022 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 4/11/2022 | Approved | DEANDRE HOFFMAN |
| Final | 5/12/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 5/12/2022 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 5/12/2022 | No Access for Inspection | JAVIER RAMOS JR |
| Final | 6/17/2022 | Permit Finaled | JAVIER RAMOS JR |
| Smoke Detectors | 6/17/2022 | Approved | JAVIER RAMOS JR |