11263 W BLIX ST 91602
Certificate Information: 11263 W BLIX ST 91602
- Application / Permit
- 21016-20000-14983
- Plan Check / Job No.
- B21VN07293
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 54' 3" X 22' 10" DETACHED GARAGE/REC ROOM TO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 6/23/2022
- Issuing Office
- Current Status
- CofO Issued on 12/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/14/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 6/15/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 10/23/2021 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 10/28/2021 | APPLICANT |
| Issued | 6/23/2022 | APPLICANT |
| CofO in Progress | 12/20/2022 | JACK KARGODORIAN |
| Permit Finaled | 12/22/2022 | MICHAEL SMITH |
| CofO Issued | 12/22/2022 | MICHAEL SMITH |
| Permit Finaled | 12/22/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/31/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/31/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/5/2022 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 7/8/2022 | Partial Approval | CALEB MEISTER |
| ELECTRICAL-Rough | 7/8/2022 | Approved | CALEB MEISTER |
| Insulation | 7/12/2022 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 7/15/2022 | Partial Approval | THOMAS FINNILA |
| Green Building Rough | 7/15/2022 | Approved | THOMAS FINNILA |
| MERV13>=Rough | 7/15/2022 | Approved | THOMAS FINNILA |
| Drywall Nailing | 7/21/2022 | Approved | THOMAS FINNILA |
| Green Building Rough | 8/16/2022 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 9/1/2022 | Approved | THOMAS FINNILA |
| Final | 9/1/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Smoke Detectors | 9/1/2022 | Corrections Issued | THOMAS FINNILA |
| Final | 11/16/2022 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 11/16/2022 | Approved | JACK KARGODORIAN |
| MERV13>=Final | 11/16/2022 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 11/16/2022 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 11/16/2022 | Approved | JACK KARGODORIAN |
| Final | 12/8/2022 | OK to Issue CofO | JACK KARGODORIAN |