9401 N CORBIN AVE 91324
Certificate Information: 9401 N CORBIN AVE 91324
- Application / Permit
- 21016-20000-14941
- Plan Check / Job No.
- B21VN07274
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (12) Manufacturing
- Work Description
- TENANT IMPROVEMENT EXISTING OFFICE/MANUFACTURING BUILDING; PARKING RESTRIPE
- Permit Issued
- Issued on 11/15/2021
- Issuing Office
- Current Status
- Issued on 11/15/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2021 | SELLA BENYAMIN |
| Corrections Issued | 8/12/2021 | SELLA BENYAMIN |
| Quality Review Completed | 8/13/2021 | STEVEN KIM |
| Building Plans Picked Up | 8/16/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 9/28/2021 | APPLICANT |
| Green Plans Picked Up | 9/28/2021 | APPLICANT |
| Plan Check Approved | 11/5/2021 | SELLA BENYAMIN |
| Issued | 11/15/2021 | APPLICANT |
Permit Application Clearance Information
| ZI | Cleared | 10/1/2021 | PABLO ESTRADA |
| Green Code | Cleared | 10/12/2021 | MICHAEL AYERS |
| DAS Clearance | Cleared | 10/14/2021 | SELLA BENYAMIN |
Contact Information
| Architect | Kellogg,, Mark Robert; Lic. No.: C22989 | 29619 AGOURA ROAD AGOURA HILLS, CA 91301 |
| Contractor | Frontline Construction Inc; Lic. No.: 944366-C36 | 3625 E THOUSAND OAKS BLVD #137 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 11/23/2021 | Not Ready for Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 11/29/2021 | Approved | DANIEL VARNUM |
| Drywall Nailing | 12/14/2021 | Approved | JEFFREY FULTON |
| Drywall Nailing | 1/4/2022 | Approved | JEFFREY FULTON |
| Excavation/Setback/Form/Re-Bar | 1/10/2022 | Partial Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 1/18/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Drywall Nailing | 1/25/2023 | Partial Approval | DEANDRE HOFFMAN |
| T-Bar Ceiling | 7/24/2023 | Partial Inspection | DEANDRE HOFFMAN |
| T-Bar Ceiling | 1/10/2024 | Approved | DEANDRE HOFFMAN |
| Final | 3/6/2024 | Corrections Issued | DEANDRE HOFFMAN |
| Green Building Final | 3/6/2024 | Approved | DEANDRE HOFFMAN |
| Green Building Rough | 3/6/2024 | Approved | DEANDRE HOFFMAN |
| Reinforced Masonry Frame | 3/6/2024 | Approved | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 3/6/2024 | SGSOV Approved | DEANDRE HOFFMAN |
| Smoke Detectors | 3/6/2024 | Approved | DEANDRE HOFFMAN |