8507-8509 N FULLBRIGHT AVE 91306
Certificate Information: 8507-8509 N FULLBRIGHT AVE 91306
- Application / Permit
- 21016-20000-14856
- Plan Check / Job No.
- B21VN07233
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT THE (E) ATTACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT. COMPLY WITH DEPARTMENT ORDER effective date 05/22/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 11/7/2021
- Issuing Office
- Current Status
- Issued on 11/7/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2021 | JESSE ARELLANO |
| Corrections Issued | 7/24/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 8/25/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 9/28/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 11/1/2021 | JESSE ARELLANO |
| Issued | 11/7/2021 | APPLICANT |
| Building Plans Picked Up | 11/8/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/1/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 10/1/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/1/2021 | CARLOS AGUILERA |
| Green Code | Cleared | 11/1/2021 | JESSE ARELLANO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| FELIPE PENICHE, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/9/2021 | Approved | RICHARD SIMONS |
| BUILDING-Rough-Frame | 2/14/2025 | Not Ready for Inspection | JOEL GUARDADO |
| Green Building Rough | 2/14/2025 | Not Ready for Inspection | JOEL GUARDADO |
| Reinforced Concrete Frame | 2/14/2025 | Not Ready for Inspection | JOEL GUARDADO |
| Wood Frame | 2/14/2025 | Not Ready for Inspection | JOEL GUARDADO |
| BUILDING-Rough-Frame | 2/19/2025 | Partial Inspection | JOEL GUARDADO |
| ELECTRICAL-Final | 2/19/2025 | Corrections Issued | JOEL GUARDADO |
| Green Building Rough | 2/19/2025 | Partial Inspection | JOEL GUARDADO |
| Insulation | 2/19/2025 | Partial Inspection | JOEL GUARDADO |
| Reinforced Concrete Frame | 2/19/2025 | Not Ready for Inspection | JOEL GUARDADO |
| Reinforced Masonry Frame | 2/19/2025 | Not Ready for Inspection | JOEL GUARDADO |
| Wood Frame | 2/19/2025 | Not Ready for Inspection | JOEL GUARDADO |
| ELECTRICAL-Rough | 4/29/2025 | Not Ready for Inspection | JOEL GUARDADO |
| Insulation | 4/29/2025 | Partial Approval | JOEL GUARDADO |
| Wood Frame | 4/29/2025 | Not Ready for Inspection | JOEL GUARDADO |
| ELECTRICAL-Final | 5/2/2025 | Partial Inspection | JOEL GUARDADO |
| Wood Frame | 5/2/2025 | Corrections Issued | JOEL GUARDADO |
| BUILDING-Rough-Frame | 8/26/2025 | Approved | JOEL GUARDADO |
| Final | 8/26/2025 | Not Ready for Inspection | JOEL GUARDADO |
| Green Building Final | 8/26/2025 | Not Ready for Inspection | JOEL GUARDADO |
| Green Building Rough | 8/26/2025 | Approved | JOEL GUARDADO |
| SGSOV-Seismic Gas S/O Valve | 8/26/2025 | SGSOV Not Ready | JOEL GUARDADO |
| Smoke Detectors | 8/26/2025 | Not Ready for Inspection | JOEL GUARDADO |
| ELECTRICAL-Final | 11/7/2025 | Not Ready for Inspection | MARIYA MIHALEVA |
| Final | 11/7/2025 | Corrections Issued | MARIYA MIHALEVA |
| Green Building Final | 11/7/2025 | Not Ready for Inspection | MARIYA MIHALEVA |
| HVAC-Final | 11/7/2025 | Not Ready for Inspection | MARIYA MIHALEVA |
| PLUMBING-Final | 11/7/2025 | Not Ready for Inspection | MARIYA MIHALEVA |
| SGSOV-Seismic Gas S/O Valve | 11/7/2025 | SGSOV Not Ready | MARIYA MIHALEVA |
| Smoke Detectors | 11/7/2025 | Not Ready for Inspection | MARIYA MIHALEVA |
| Final | 2/20/2026 | Partial Inspection | JOSE RUBIO |
| Green Building Final | 2/20/2026 | Not Ready for Inspection | JOSE RUBIO |
| SGSOV-Seismic Gas S/O Valve | 2/20/2026 | SGSOV Not Ready | JOSE RUBIO |
| Smoke Detectors | 2/20/2026 | Not Ready for Inspection | JOSE RUBIO |