13460 N LEXICON AVE 91342
Certificate Information: 13460 N LEXICON AVE 91342
- Application / Permit
- 21016-20000-14808
- Plan Check / Job No.
- B21VN07178
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER CA GOV. STATE CODE 65852.2(e)(1)(A). WORK PER WFPP AND ENGINEER DETAIL.
- Permit Issued
- Issued on 4/1/2022
- Issuing Office
- Current Status
- CofO Issued on 4/11/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2021 | ROSENDO MEDINA |
| Corrections Issued | 7/10/2021 | ROSENDO MEDINA |
| Applicant returned to address corrections | 10/29/2021 | ROSENDO MEDINA |
| Applicant returned to address corrections | 2/24/2022 | ROSENDO MEDINA |
| Plan Check Approved | 3/23/2022 | ROSENDO MEDINA |
| Building Plans Picked Up | 3/23/2022 | APPLICANT |
| Issued | 4/1/2022 | APPLICANT |
| CofO in Progress | 4/5/2024 | DAVID ANDERSON |
| Permit Finaled | 4/11/2024 | RUBEN SALAS |
| CofO Issued | 4/11/2024 | RUBEN SALAS |
| Permit Finaled | 4/11/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/19/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/19/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/22/2021 | CARLOS AGUILERA |
| ZA Case | Cleared | 2/11/2022 | MARITZA PRZEKOP |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Azarbin,, Hamid; Lic. No.: C64515 | 22655 COVELLO ST WEST HILLS, CA 91307 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 9/16/2022 | Approved | CALEB MEISTER |
| Gas Test | 9/21/2022 | Partial Approval | ASHLEY THOMPSON |
| PLUMBING-Rough | 9/21/2022 | Partial Approval | ASHLEY THOMPSON |
| Excavation/Setback/Form/Re-Bar | 9/22/2022 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 9/23/2022 | Approved | ARAM AVEDISIAN |
| Underground Mechanical | 9/23/2022 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 10/14/2022 | Approved | ARAM AVEDISIAN |
| Gas Test | 10/14/2022 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 10/19/2022 | Corrections Issued | ARAM AVEDISIAN |
| Wood Frame | 10/19/2022 | Corrections Issued | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 10/21/2022 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 10/21/2022 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 10/21/2022 | Conditional Approval | ARAM AVEDISIAN |
| HVAC-Rough | 10/21/2022 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 10/21/2022 | Approved | ARAM AVEDISIAN |
| Insulation | 10/24/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 10/24/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 10/25/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 10/26/2022 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 10/31/2022 | Approved | MATTHEW NELSON |
| Insulation | 10/31/2022 | Partial Approval | MATTHEW NELSON |
| Interior/Exterior Lathing | 10/31/2022 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 11/4/2022 | Approved | MATTHEW NELSON |
| Shower Pan | 11/4/2022 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 1/17/2023 | Approved | JOHN COLEMAN |
| Final | 1/17/2023 | Corrections Issued | JOHN COLEMAN |
| Green Building Final | 1/17/2023 | Corrections Issued | JOHN COLEMAN |
| Green Building Rough | 1/17/2023 | Approved | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 1/17/2023 | SGSOV Not Ready | JOHN COLEMAN |
| Smoke Detectors | 1/17/2023 | Approved | JOHN COLEMAN |
| Final | 2/8/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Green Building Final | 2/8/2023 | Approved | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 2/8/2023 | SGSOV Approved | JOHN COLEMAN |
| Final | 2/14/2023 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 2/14/2023 | Not Ready for Inspection | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 2/14/2023 | SGSOV Not Ready | DAVID ANDERSON |
| Final | 2/23/2023 | OK to Issue CofO | DAVID ANDERSON |
| Green Building Final | 2/23/2023 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 2/23/2023 | SGSOV Approved | DAVID ANDERSON |