14953 W TUBA ST 91345

Certificate Information: 14953 W TUBA ST 91345

Application / Permit
21016-20000-14725
Plan Check / Job No.
B21VN07132
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
5'-0" X 20'-0" ADDITION TO (E) GARAGE AND CONVERT INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 9/13/2021
Issuing Office
Current Status
CofO Issued on 5/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/7/2021 APPLICANT
Assigned to Plan Check Engineer 6/10/2021 ARTIN ZARUKIAN
Corrections Issued 6/12/2021 ARTIN ZARUKIAN
Plan Check Approved 9/13/2021 ARTIN ZARUKIAN
Issued 9/13/2021 APPLICANT
Building Plans Picked Up 9/22/2021 APPLICANT
CofO in Progress 5/11/2023 JENNIFER RABUCHIN
Permit Finaled 5/11/2023 MICHAEL SMITH
CofO Issued 5/11/2023 MICHAEL SMITH
Permit Finaled 5/11/2023 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 8/24/2021 RIDWAN HARDY
Address approval Cleared 8/25/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/25/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 8/25/2021 CARLOS AGUILERA
Sewer availability Cleared 8/25/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/15/2022 Partial Approval JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 3/22/2022 Corrections Issued JENNIFER RABUCHIN
Sewer 3/22/2022 Approved JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 4/14/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 6/30/2022 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 6/30/2022 Approved JOHN KIDWELL
Green Building Rough 6/30/2022 Partial Approval JOHN KIDWELL
HVAC-Rough 6/30/2022 Approved JOHN KIDWELL
PLUMBING-Rough 6/30/2022 Approved JOHN KIDWELL
BUILDING-Rough-Frame 7/11/2022 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 7/11/2022 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 7/11/2022 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/22/2022 Approved JENNIFER RABUCHIN
Green Building Rough 7/22/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 7/22/2022 Partial Approval JENNIFER RABUCHIN
Insulation 8/4/2022 Approved JENNIFER RABUCHIN
Drywall Nailing 9/1/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 9/1/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 11/4/2022 Corrections Issued JENNIFER RABUCHIN
Final 11/4/2022 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 11/4/2022 Approved JENNIFER RABUCHIN
Green Building Final 11/4/2022 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 11/4/2022 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 11/4/2022 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 11/4/2022 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 11/4/2022 Corrections Issued JENNIFER RABUCHIN
Smoke Detectors 11/4/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 5/11/2023 Approved JENNIFER RABUCHIN
Final 5/11/2023 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 5/11/2023 Approved JENNIFER RABUCHIN
HVAC-Final 5/11/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 5/11/2023 Approved JENNIFER RABUCHIN
Service/Power Release 5/11/2023 Approved JENNIFER RABUCHIN