3300 S COMPTON AVE 90011

Certificate Information: 3300 S COMPTON AVE 90011

Application / Permit
21016-20000-14708
Plan Check / Job No.
B21VN07123
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) IRREGULAR 26'-0" X 50'-0" RETAIL TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(A), EXISTING ATTACHED SFD TO REMAIN. ALL WORK PER WFPP.
Permit Issued
Issued on 6/23/2021
Issuing Office
Current Status
CofO Issued on 8/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/8/2021 APPLICANT
Assigned to Plan Check Engineer 6/8/2021 JENNIFER LEE
Corrections Issued 6/8/2021 JENNIFER LEE
Building Plans Picked Up 6/9/2021 APPLICANT
Plan Check Approved 6/23/2021 JENNIFER LEE
Issued 6/23/2021 APPLICANT
CofO in Progress 6/16/2022 JOAQUIN GREENOUGH
Permit Finaled 8/4/2022 DEROLD HAUFF
CofO Issued 8/4/2022 DEROLD HAUFF
Permit Finaled 8/4/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/18/2021 WALLIE JONG
Redevelopment Project Area Cleared 6/18/2021 GRACIELA ACOSTA
Eng Process Fee Ord 176,300 Cleared 6/22/2021 WALLIE JONG
Sewer availability Cleared 6/22/2021 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/27/2021 Approved SABAS ALONSO
BUILDING-Rough-Frame 12/13/2021 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Rough 12/13/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Green Building Rough 12/13/2021 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Rough 12/13/2021 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Rough 12/16/2021 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 12/16/2021 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 1/6/2022 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Rough 1/6/2022 Approved JOAQUIN GREENOUGH
Green Building Rough 1/6/2022 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Rough 1/6/2022 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 1/12/2022 Approved JOAQUIN GREENOUGH
Footing/Foundation/Slab 1/12/2022 Approved JOAQUIN GREENOUGH
Green Building Rough 1/12/2022 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 1/12/2022 Partial Approval JOAQUIN GREENOUGH
Insulation 1/19/2022 Approved JOAQUIN GREENOUGH
Drywall Nailing 1/26/2022 Partial Approval JOAQUIN GREENOUGH
Drywall Nailing 2/1/2022 Approved JOAQUIN GREENOUGH
Final 6/2/2022 Corrections Issued JOAQUIN GREENOUGH
Green Building Final 6/2/2022 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 6/2/2022 SGSOV Approved JOAQUIN GREENOUGH
Smoke Detectors 6/2/2022 Approved JOAQUIN GREENOUGH
Final 6/15/2022 OK to Issue CofO JOAQUIN GREENOUGH