2520 W 7TH ST 1-31 90057
Certificate Information: 2520 W 7TH ST 1-31 90057
- Application / Permit
- 21016-20000-14627
- Plan Check / Job No.
- B21VN07079
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT (E) 55'-7" X 21'-7" STORAGE ROOM TO ACCESSORY DWELLING UNIT (1199 SQ FT) PER GCS 65852.2(e)(1)(C)
- Permit Issued
- Issued on 10/14/2021
- Issuing Office
- Current Status
- Issued on 10/14/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/11/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 6/12/2021 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 10/13/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 10/14/2021 | JEROME MAGAT PALMA |
| Issued | 10/14/2021 | APPLICANT |
| Building Plans Picked Up | 10/20/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/8/2021 | THOMAS LANG |
| Sewer availability | Cleared | 7/8/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 7/16/2021 | THOMAS LANG |
| Redevelopment Project Area | Cleared | 9/29/2021 | GRACIELA ACOSTA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/3/2022 | Approved | TIMOTHY BUXTON |
| Final | 1/26/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Green Building Final | 1/26/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Green Building Rough | 1/26/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| SGSOV-Seismic Gas S/O Valve | 1/26/2023 | SGSOV Not Ready | RAMAZANALI ALMASI |
| Smoke Detectors | 1/26/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Wood Frame | 1/26/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Final | 4/10/2023 | Conditional Approval | RAMAZANALI ALMASI |
| Green Building Final | 4/10/2023 | Approved | RAMAZANALI ALMASI |
| Green Building Rough | 4/10/2023 | Approved | RAMAZANALI ALMASI |
| SGSOV-Seismic Gas S/O Valve | 4/10/2023 | SGSOV Approved | RAMAZANALI ALMASI |
| Smoke Detectors | 4/10/2023 | Approved | RAMAZANALI ALMASI |
| Wood Frame | 4/10/2023 | Approved | RAMAZANALI ALMASI |
| Final | 4/14/2023 | Partial Approval | RAMAZANALI ALMASI |