5045-5047 N BELLAIRE AVE 91607

Certificate Information: 5045-5047 N BELLAIRE AVE 91607

Application / Permit
21016-20000-14624
Plan Check / Job No.
B21VN07075
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO ATTACHED ADU PER STATE LAW (1-STORY)
Permit Issued
Issued on 8/17/2021
Issuing Office
Current Status
CofO Issued on 6/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/7/2021 APPLICANT
Assigned to Plan Check Engineer 6/9/2021 CARLOS MONTES
Corrections Issued 6/9/2021 CARLOS MONTES
Plan Check Approved 8/4/2021 KEVIN MORALES
Issued 8/17/2021 APPLICANT
CofO in Progress 3/8/2022 CHRISTOPHE COCHRAN
CofO in Progress 3/8/2022 CHRISTOPHE COCHRAN
CofO Issued 6/8/2022 MICHAEL SMITH
Permit Finaled 6/8/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/2/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 7/2/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 7/7/2021 DAGOVERTO GUERRERO
Specific Plan Cleared 7/28/2021 CORREY KITCHENS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/5/2021 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 10/5/2021 Partial Approval CHRISTOPHE COCHRAN
ELECTRICAL-Rough 10/28/2021 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 10/28/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 11/10/2021 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 11/10/2021 Approved CHRISTOPHE COCHRAN
Insulation 11/10/2021 Partial Approval CHRISTOPHE COCHRAN
Interior/Exterior Lathing 11/10/2021 Partial Approval CHRISTOPHE COCHRAN
PLUMBING-Rough 11/10/2021 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 11/16/2021 Approved ASHLEY THOMPSON
Insulation 11/16/2021 Conditional Approval ASHLEY THOMPSON
Drywall Nailing 11/29/2021 Approved JACK KARGODORIAN
Interior/Exterior Lathing 11/29/2021 Approved JACK KARGODORIAN
Footing/Foundation/Slab 1/6/2022 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 2/18/2022 Approved CHRISTOPHE COCHRAN
Final 2/18/2022 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 2/18/2022 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 2/18/2022 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 2/18/2022 Approved CHRISTOPHE COCHRAN
Final 3/8/2022 OK to Issue CofO CHRISTOPHE COCHRAN