5045-5047 N BELLAIRE AVE 91607
Certificate Information: 5045-5047 N BELLAIRE AVE 91607
- Application / Permit
- 21016-20000-14624
- Plan Check / Job No.
- B21VN07075
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE TO ATTACHED ADU PER STATE LAW (1-STORY)
- Permit Issued
- Issued on 8/17/2021
- Issuing Office
- Current Status
- CofO Issued on 6/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2021 | CARLOS MONTES |
| Corrections Issued | 6/9/2021 | CARLOS MONTES |
| Plan Check Approved | 8/4/2021 | KEVIN MORALES |
| Issued | 8/17/2021 | APPLICANT |
| CofO in Progress | 3/8/2022 | CHRISTOPHE COCHRAN |
| CofO in Progress | 3/8/2022 | CHRISTOPHE COCHRAN |
| CofO Issued | 6/8/2022 | MICHAEL SMITH |
| Permit Finaled | 6/8/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/2/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/2/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2021 | DAGOVERTO GUERRERO |
| Specific Plan | Cleared | 7/28/2021 | CORREY KITCHENS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/5/2021 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 10/5/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 10/28/2021 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 10/28/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 11/10/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| Green Building Rough | 11/10/2021 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 11/10/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 11/10/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 11/10/2021 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2021 | Approved | ASHLEY THOMPSON |
| Insulation | 11/16/2021 | Conditional Approval | ASHLEY THOMPSON |
| Drywall Nailing | 11/29/2021 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 11/29/2021 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 1/6/2022 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 2/18/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 2/18/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 2/18/2022 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 2/18/2022 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 2/18/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 3/8/2022 | OK to Issue CofO | CHRISTOPHE COCHRAN |