8250 N WOODLEY AVE 91406

Certificate Information: 8250 N WOODLEY AVE 91406

Application / Permit
21016-20000-14544
Plan Check / Job No.
B21VN07057
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
NEW EQUIPMENT PLATFORMS IN (E) INDUSTRIAL WAREHOUSE BUILDING
Permit Issued
Issued on 11/4/2021
Issuing Office
Current Status
Issued on 11/4/2021

Permit Application Status History

Submitted 6/29/2021 APPLICANT
Green Plans Picked Up 7/12/2021 APPLICANT
Disabled Access Plans Picked Up 7/13/2021 APPLICANT
Assigned to Plan Check Engineer 7/29/2021 MARVEL DELACRUZ
Corrections Issued 8/3/2021 MARVEL DELACRUZ
Quality Review Completed 8/13/2021 STEVEN KIM
Building Plans Picked Up 8/16/2021 APPLICANT
Applicant returned to address corrections 9/24/2021 MARVEL DELACRUZ
Applicant returned to address corrections 9/29/2021 MARVEL DELACRUZ
Plan Check Approved 11/4/2021 MARVEL DELACRUZ
Issued 11/4/2021 APPLICANT

Permit Application Clearance Information

Green Code Cleared 9/14/2021 MICHAEL AYERS
DAS Clearance Cleared 9/16/2021 MARVEL DELACRUZ

Contact Information

Contractor Advanced Constructors Corp; Lic. No.: 643603-B P O BOX 1578      HUNTINGTON BEACH, CA 92647
Engineer Boyd,, Ellyssa Ann; Lic. No.: C84836 1227 W PALM AVE      ORANGE, CA 92868

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/18/2021 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 11/18/2021 Conditional Approval JEFFREY FULTON
Deputy Drilled-In Anchors 11/19/2021 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 11/19/2021 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 12/1/2021 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 12/6/2021 Conditional Approval JEFFREY FULTON
Deputy Drilled-In Anchors 1/3/2022 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 1/3/2022 Conditional Approval JEFFREY FULTON
Deputy Drilled-In Anchors 5/6/2022 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 5/6/2022 Conditional Approval JEFFREY FULTON
Deputy Drilled-In Anchors 5/9/2022 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 5/9/2022 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 9/18/2023 Conditional Approval DEANDRE HOFFMAN
Deputy Steel/Welding 9/19/2023 Conditional Approval DEANDRE HOFFMAN
Deputy Steel/Welding 12/27/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 12/30/2024 Conditional Approval GREGORY POMISH
Structural Steel Frame 3/4/2026 Approved EDWIN GREGORYONA