3841 W 59TH ST 90043

Certificate Information: 3841 W 59TH ST 90043

Application / Permit
21016-20000-14474
Plan Check / Job No.
B21VN07001
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 16'-1" X 18'-2" DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER DESIGN.
Permit Issued
Issued on 8/24/2021
Issuing Office
Current Status
CofO Issued on 9/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/4/2021 APPLICANT
Assigned to Plan Check Engineer 6/7/2021 RAPHAEL ROSAS
Corrections Issued 6/8/2021 RAPHAEL ROSAS
Issued 8/24/2021 APPLICANT
Building Plans Picked Up 8/27/2021 APPLICANT
CofO in Progress 8/31/2023 ENRIQUE MIRELES
Permit Finaled 9/5/2023 DEROLD HAUFF
CofO Issued 9/5/2023 DEROLD HAUFF
Permit Finaled 9/5/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/15/2021 RENZ SORIANO
Sewer availability Cleared 6/15/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 6/16/2021 RENZ SORIANO
Construction near power lines Cleared 8/9/2021 RIDWAN HARDY

Contact Information

Architect Miller,, Michael; Lic. No.: C26956 12756 MITCHELL AVE      LOS ANGELES, CA 90066
Contractor South Land Remodeling Inc; Lic. No.: 901842-B 10770 DES MOINES AVE      NORTHRIDGE, CA 91326

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/29/2021 Approved ALAN MORELOS
Excavation/Setback/Form/Re-Bar 10/7/2021 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 10/19/2021 Partial Approval FREDDIE RIVERA
Footing/Foundation/Slab 10/22/2021 Approved FREDDIE RIVERA
Wood Frame 11/9/2021 Corrections Issued FREDDIE RIVERA
BUILDING-Rough-Frame 12/7/2021 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Rough 12/7/2021 Approved JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 12/7/2021 Approved JOAQUIN GREENOUGH
Green Building Rough 12/7/2021 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Rough 12/7/2021 Approved JOAQUIN GREENOUGH
Wood Frame 12/7/2021 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 12/14/2021 Not Ready for Inspection FREDDIE RIVERA
Green Building Rough 12/14/2021 Corrections Issued FREDDIE RIVERA
Wood Frame 12/14/2021 Not Ready for Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 12/30/2021 Approved FREDDIE RIVERA
Green Building Rough 12/30/2021 Approved FREDDIE RIVERA
Insulation 12/30/2021 Partial Approval FREDDIE RIVERA
Interior/Exterior Lathing 12/30/2021 Conditional Approval FREDDIE RIVERA
Insulation 1/10/2022 Approved HORACE FULTZ
Wood Frame 1/10/2022 Not Ready for Inspection HORACE FULTZ
Insulation 1/14/2022 Approved FREDDIE RIVERA
Interior/Exterior Lathing 1/19/2022 Approved FREDDIE RIVERA
Shower Pan 1/19/2022 Approved FREDDIE RIVERA
Deputy Wood Construction 1/24/2022 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 1/24/2022 Approved FREDDIE RIVERA
Drywall Nailing 2/7/2022 Approved FREDDIE RIVERA
Final 4/7/2022 Corrections Issued ENRIQUE MIRELES
Green Building Final 4/7/2022 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 4/7/2022 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 4/7/2022 Approved ENRIQUE MIRELES
Final 6/2/2022 Corrections Issued ENRIQUE MIRELES
Final 6/9/2022 OK to Issue CofO ENRIQUE MIRELES