4416 N GENTRY AVE 91607

Certificate Information: 4416 N GENTRY AVE 91607

Application / Permit
21016-20000-14419
Plan Check / Job No.
B21VN06971
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL TO ALL BATHROOMS, RECONFIGURE THE MASTER SUITE AND REPLACE THE FIREPLACE.
Permit Issued
Issued on 12/30/2021
Issuing Office
Current Status
Permit Finaled on 4/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/4/2021 APPLICANT
Assigned to Plan Check Engineer 6/7/2021 ALFRED RAMIREZ
Corrections Issued 6/7/2021 PINANK PATEL
Plan Check Approved 9/20/2021 PINANK PATEL
Building Plans Picked Up 9/21/2021 APPLICANT
Issued 12/30/2021 APPLICANT
Permit Finaled 4/17/2025 JAVIER RAMOS JR

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Ko General Construction; Lic. No.: 1046527-B 12940 MACNEIL      SYLMAR, CA 91342

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/18/2022 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 5/4/2022 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/19/2022 Conditional Approval THOMAS FINNILA
BUILDING-Rough-Frame 8/3/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 8/3/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Rough 8/3/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Deputy Wood Construction 8/4/2022 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 8/5/2022 Corrections Issued THOMAS FINNILA
HVAC-Rough 8/5/2022 Corrections Issued THOMAS FINNILA
Interior/Exterior Lathing 9/20/2022 Not Ready for Inspection CALEB MEISTER
BUILDING-Rough-Frame 9/23/2022 Corrections Issued THOMAS FINNILA
Interior/Exterior Lathing 9/23/2022 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 10/17/2022 Corrections Issued JACK KARGODORIAN
HVAC-Rough 10/17/2022 Approved JACK KARGODORIAN
PLUMBING-Rough 10/17/2022 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 10/24/2022 Approved JACK KARGODORIAN
Insulation 10/28/2022 Approved CALEB MEISTER
Insulation 10/28/2022 Off-Hour Fees Due
Drywall Nailing 11/14/2022 Approved JACK KARGODORIAN
Interior/Exterior Lathing 1/17/2023 Approved RYAN SALAZAR
Shower Pan 1/17/2023 Approved RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 4/27/2023 Partial Approval JOHN COLEMAN
Footing/Foundation/Slab 5/5/2023 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 5/12/2023 Approved JACK KARGODORIAN
Wood Frame 5/12/2023 Not Ready for Inspection JACK KARGODORIAN
Deputy Reinf. Concrete 5/15/2023 Conditional Approval MICHAEL SMITH
Footing/Foundation/Slab 6/27/2023 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 6/29/2023 Partial Approval DAVID MATSON
Final 7/27/2023 Corrections Issued JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 7/27/2023 SGSOV Not Ready JACK KARGODORIAN
Smoke Detectors 7/27/2023 Approved JACK KARGODORIAN
Final 8/4/2023 Corrections Issued JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 8/4/2023 SGSOV Not Ready JACK KARGODORIAN
Final 3/29/2024 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 3/29/2024 SGSOV Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 4/17/2025 Approved JAVIER RAMOS JR
Final 4/17/2025 Permit Finaled JAVIER RAMOS JR
Green Building Final 4/17/2025 Approved JAVIER RAMOS JR