1600 N PALISADES DR 90272
Certificate Information: 1600 N PALISADES DR 90272
- Application / Permit
- 21016-20000-14412
- Plan Check / Job No.
- B21VN06966
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (35) Condo-Multi Family
- Work Description
- ADD & EXPAND (9'-2"x 7'-3") EXISTING MAIN ENTRY AT FIRST FLOOR, CONVERT/ ENCLOSE (E) 2ND FLOOR BALCONY TO NEW OFFICE ROOM, INTERIOR REMODEL BETWEEN KITCHEN & CONVERT (E) FAMILY ROOM TO BEDROOM. WORK PER ENGINEER.
- Permit Issued
- Issued on 2/22/2022
- Issuing Office
- Current Status
- CofO Issued on 5/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2021 | TROY DEGUZMAN |
| Corrections Issued | 7/28/2021 | TROY DEGUZMAN |
| Quality Review Completed | 8/4/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 8/13/2021 | APPLICANT |
| Plan Check Approved | 1/20/2022 | TROY DEGUZMAN |
| Issued | 2/22/2022 | APPLICANT |
| CofO in Progress | 5/15/2023 | GRANT WOODS |
| Permit Finaled | 5/16/2023 | DAVID TSAU |
| CofO Issued | 5/16/2023 | DAVID TSAU |
| Permit Finaled | 5/16/2023 | DAVID TSAU |
Permit Application Clearance Information
| Miscellaneous | Cleared | 9/1/2021 | LAUREN PADICK |
| Eng Process Fee Ord 176,300 | Cleared | 9/3/2021 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 9/3/2021 | ANTHONY MAINEZ |
| ZA Case | Cleared | 11/3/2021 | STEVEN WECHSLER |
| Coastal Zone | Cleared | 12/15/2021 | STEVEN WECHSLER |
| Green Code | Cleared | 1/20/2022 | TROY DEGUZMAN |
Contact Information
| Contractor | Liebobuilders; Lic. No.: 1054050-B | 18401 BURBANK BLVD SUITE 120 TARZANA, CA 91356 |
| Engineer | Wu,, Harold Ping-Hung; Lic. No.: C35693 | 1168 SAN GABRIEL BLVD NO N ROSEMEAD, CA 91770 |
Inspector Information
| CASIMIR BRITTON, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
| SHAVONNE ESPINOZA, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/25/2022 | Partial Approval | GRANT WOODS |
| Footing/Foundation/Slab | 8/11/2022 | Corrections Issued | SORIN CIRSTOIU |
| FLOOD-Proofing Certificate | 9/16/2022 | Approved | SORIN CIRSTOIU |
| Green Building Rough | 9/16/2022 | Partial Inspection | SORIN CIRSTOIU |
| Wood Frame | 9/16/2022 | Partial Inspection | SORIN CIRSTOIU |
| Green Building Rough | 9/29/2022 | Approved | GRANT WOODS |
| Wood Frame | 9/29/2022 | Approved | GRANT WOODS |
| Drywall Nailing | 10/7/2022 | Approved | GRANT WOODS |
| Final | 5/2/2023 | Corrections Issued | SORIN CIRSTOIU |
| Footing/Foundation/Slab | 5/2/2023 | Partial Inspection | SORIN CIRSTOIU |
| Green Building Final | 5/2/2023 | Partial Inspection | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 5/2/2023 | SGSOV Not Ready | SORIN CIRSTOIU |
| Smoke Detectors | 5/2/2023 | Partial Inspection | SORIN CIRSTOIU |
| Final | 5/5/2023 | Not Ready for Inspection | GRANT WOODS |
| Footing/Foundation/Slab | 5/5/2023 | Approved | GRANT WOODS |
| Green Building Final | 5/5/2023 | Approved | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 5/5/2023 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 5/5/2023 | Approved | GRANT WOODS |
| Final | 5/15/2023 | Conditional Approval | GRANT WOODS |