16017-16019 W CALAHAN ST 91343
Certificate Information: 16017-16019 W CALAHAN ST 91343
- Application / Permit
- 21016-20000-14377
- Plan Check / Job No.
- B21VN06943
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT THE (E) 23'0" X 19'0" GARAGE INTO A (N) JR. ACCESSORY DWELLING UNIT. ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 4/4/2022
- Issuing Office
- Current Status
- CofO Issued on 12/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/4/2021 | MARVEL DELACRUZ |
| Corrections Issued | 6/4/2021 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 8/17/2021 | MARVEL DELACRUZ |
| Building Plans Picked Up | 1/14/2022 | APPLICANT |
| Applicant returned to address corrections | 2/10/2022 | MARVEL DELACRUZ |
| Plan Check Approved | 3/2/2022 | MARVEL DELACRUZ |
| Issued | 4/4/2022 | APPLICANT |
| CofO in Progress | 12/2/2024 | JENNIFER RABUCHIN |
| Permit Finaled | 12/4/2024 | RUBEN SALAS |
| CofO Issued | 12/4/2024 | RUBEN SALAS |
| Permit Finaled | 12/4/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/30/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/30/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/30/2021 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 7/14/2021 | BRIAN MILLER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vasquez,, Mario Alberto; Lic. No.: C89006 | 43023 40TH ST WEST LANCASTER, CA 93536 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/12/2022 | Partial Approval | RAUL OLAGI |
| Sewer | 5/12/2022 | Partial Approval | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 6/24/2022 | Not Ready for Inspection | ALAN MORELOS |
| Footing/Foundation/Slab | 7/29/2022 | Approved | ALAN MORELOS |
| Footing/Foundation/Slab | 10/24/2022 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 3/26/2024 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 3/26/2024 | Corrections Issued | RAUL OLAGI |
| Green Building Rough | 3/26/2024 | Not Ready for Inspection | RAUL OLAGI |
| HVAC-Rough | 3/26/2024 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 3/26/2024 | Corrections Issued | RAUL OLAGI |
| Sewer | 3/26/2024 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 4/17/2024 | Approved | RAUL OLAGI |
| Green Building Rough | 4/17/2024 | Approved | RAUL OLAGI |
| Rough-Elec/Plmb/HVAC | 4/17/2024 | Approved | RAUL OLAGI |
| Insulation | 4/22/2024 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 4/22/2024 | Partial Approval | RAUL OLAGI |
| Shower Pan | 4/22/2024 | Not Ready for Inspection | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Gas Test | 5/20/2024 | Approved | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2024 | Approved | RAUL OLAGI |
| Drywall Nailing | 9/16/2024 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 9/16/2024 | Approved | RAUL OLAGI |
| Shower Pan | 9/16/2024 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 11/19/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 11/19/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 11/19/2024 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Final | 11/19/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 11/19/2024 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 11/19/2024 | SGSOV Approved | SALVADOR MARTINEZ |
| Service/Power Release | 11/19/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Smoke Detectors | 11/19/2024 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 11/27/2024 | Approved | JENNIFER RABUCHIN |
| Final | 11/27/2024 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 11/27/2024 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 11/27/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 11/27/2024 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 11/27/2024 | Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 11/27/2024 | Approved | JENNIFER RABUCHIN |