2040 1/2 W 28TH ST 90018

Certificate Information: 2040 1/2 W 28TH ST 90018

Application / Permit
21016-20000-14375
Plan Check / Job No.
B21VN06940
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) and (d). SEE COMMENTS.
Permit Issued
Issued on 9/30/2021
Issuing Office
Current Status
CofO Issued on 5/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/3/2021 APPLICANT
Assigned to Plan Check Engineer 6/4/2021 HAYATO TSUCHIYA
Corrections Issued 6/5/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 9/13/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 9/14/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 9/30/2021 HAYATO TSUCHIYA
Plan Check Approved 9/30/2021 HAYATO TSUCHIYA
Issued 9/30/2021 APPLICANT
Building Plans Picked Up 10/1/2021 APPLICANT
CofO in Progress 5/19/2023 SABAS ALONSO
Permit Finaled 5/21/2023 DEROLD HAUFF
CofO Issued 5/21/2023 DEROLD HAUFF
Permit Finaled 5/21/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/11/2021 CECILIO NAVARRO
Sewer availability Cleared 6/11/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 6/14/2021 CECILIO NAVARRO
HPOZ Cleared 6/30/2021 MAX LODER
Miscellaneous Cleared 6/30/2021 MAX LODER
ZI Cleared 6/30/2021 MAX LODER
Construction near power lines Cleared 8/31/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/1/2021 Conditional Approval JUSTIN HAWLEY
Footing/Foundation/Slab 12/6/2021 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 3/7/2022 Corrections Issued SABAS ALONSO
Gas Test 3/16/2022 Partial Approval SABAS ALONSO
Sewer 3/16/2022 Corrections Issued SABAS ALONSO
Underground Mechanical 3/16/2022 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 4/27/2022 Approved SABAS ALONSO
ELECTRICAL-Rough 4/27/2022 Approved SABAS ALONSO
Green Building Rough 4/27/2022 Approved SABAS ALONSO
Interior/Exterior Lathing 4/27/2022 Partial Approval SABAS ALONSO
METHANE-Rough 4/27/2022 Approved SABAS ALONSO
PLUMBING-Rough 4/27/2022 Approved SABAS ALONSO
HVAC-Rough 5/12/2022 Approved HORACE FULTZ
Insulation 5/12/2022 Approved HORACE FULTZ
Drywall Nailing 5/19/2022 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 5/19/2022 Approved LILIANA PORTILLO
Shower Pan 5/19/2022 Approved LILIANA PORTILLO
Drywall Nailing 5/25/2022 Approved SABAS ALONSO
ELECTRICAL-Final 8/9/2022 Approved SABAS ALONSO
Final 8/9/2022 Corrections Issued SABAS ALONSO
Green Building Final 8/9/2022 Approved SABAS ALONSO
PLUMBING-Final 8/9/2022 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 8/9/2022 SGSOV Approved SABAS ALONSO
Smoke Detectors 8/9/2022 Approved SABAS ALONSO
Final 8/16/2022 Corrections Issued SABAS ALONSO
Final 12/14/2022 Corrections Issued SABAS ALONSO
Final 5/12/2023 Corrections Issued SABAS ALONSO
Final 5/18/2023 OK to Issue CofO SABAS ALONSO