2040 1/2 W 28TH ST 90018
Certificate Information: 2040 1/2 W 28TH ST 90018
- Application / Permit
- 21016-20000-14375
- Plan Check / Job No.
- B21VN06940
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) and (d). SEE COMMENTS.
- Permit Issued
- Issued on 9/30/2021
- Issuing Office
- Current Status
- CofO Issued on 5/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/4/2021 | HAYATO TSUCHIYA |
| Corrections Issued | 6/5/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 9/13/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 9/14/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 9/30/2021 | HAYATO TSUCHIYA |
| Plan Check Approved | 9/30/2021 | HAYATO TSUCHIYA |
| Issued | 9/30/2021 | APPLICANT |
| Building Plans Picked Up | 10/1/2021 | APPLICANT |
| CofO in Progress | 5/19/2023 | SABAS ALONSO |
| Permit Finaled | 5/21/2023 | DEROLD HAUFF |
| CofO Issued | 5/21/2023 | DEROLD HAUFF |
| Permit Finaled | 5/21/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/11/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 6/11/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2021 | CECILIO NAVARRO |
| HPOZ | Cleared | 6/30/2021 | MAX LODER |
| Miscellaneous | Cleared | 6/30/2021 | MAX LODER |
| ZI | Cleared | 6/30/2021 | MAX LODER |
| Construction near power lines | Cleared | 8/31/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/1/2021 | Conditional Approval | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 12/6/2021 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 3/7/2022 | Corrections Issued | SABAS ALONSO |
| Gas Test | 3/16/2022 | Partial Approval | SABAS ALONSO |
| Sewer | 3/16/2022 | Corrections Issued | SABAS ALONSO |
| Underground Mechanical | 3/16/2022 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 4/27/2022 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 4/27/2022 | Approved | SABAS ALONSO |
| Green Building Rough | 4/27/2022 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 4/27/2022 | Partial Approval | SABAS ALONSO |
| METHANE-Rough | 4/27/2022 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 4/27/2022 | Approved | SABAS ALONSO |
| HVAC-Rough | 5/12/2022 | Approved | HORACE FULTZ |
| Insulation | 5/12/2022 | Approved | HORACE FULTZ |
| Drywall Nailing | 5/19/2022 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 5/19/2022 | Approved | LILIANA PORTILLO |
| Shower Pan | 5/19/2022 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 5/25/2022 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 8/9/2022 | Approved | SABAS ALONSO |
| Final | 8/9/2022 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 8/9/2022 | Approved | SABAS ALONSO |
| PLUMBING-Final | 8/9/2022 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 8/9/2022 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 8/9/2022 | Approved | SABAS ALONSO |
| Final | 8/16/2022 | Corrections Issued | SABAS ALONSO |
| Final | 12/14/2022 | Corrections Issued | SABAS ALONSO |
| Final | 5/12/2023 | Corrections Issued | SABAS ALONSO |
| Final | 5/18/2023 | OK to Issue CofO | SABAS ALONSO |