8035-8037 N FARRALONE AVE 91304
Certificate Information: 8035-8037 N FARRALONE AVE 91304
- Application / Permit
- 21016-20000-14158
- Plan Check / Job No.
- B21VN06810
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 19'-2" X 25' ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e). REMODEL KITCHEN OF (E )SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 7/14/2021
- Issuing Office
- Current Status
- CofO Issued on 2/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/4/2021 | RAPHAEL ROSAS |
| Corrections Issued | 6/5/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 7/6/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 7/8/2021 | APPLICANT |
| Issued | 7/14/2021 | APPLICANT |
| CofO in Progress | 2/25/2022 | TROY SANDERS |
| Permit Finaled | 2/25/2022 | JOHN JANSON |
| CofO Issued | 2/25/2022 | JOHN JANSON |
| Permit Finaled | 2/25/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/14/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 6/14/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Alpine Design And Build; Lic. No.: 948620-B | 18700 SHERMAN WAY # 210 RESEDA, CA 91335 |
| Engineer | Babapirzadeh,, Ghazal; Lic. No.: C90480 | 1530 N DETROIT ST APT 109 LOS ANGELES, CA 90046 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 7/21/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Footing/Foundation/Slab | 7/21/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| PLUMBING-Rough | 7/21/2021 | Corrections Issued | DAVID STEPANYAN |
| Sewer | 7/21/2021 | Approved | DAVID STEPANYAN |
| Footing/Foundation/Slab | 8/6/2021 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 8/6/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| PLUMBING-Rough | 8/6/2021 | Partial Approval | DAVID STEPANYAN |
| ELECTRICAL-Rough | 8/31/2021 | Corrections Issued | JEFFREY PARD |
| Gas Test | 8/31/2021 | Not Ready for Inspection | JEFFREY PARD |
| HVAC-Rough | 8/31/2021 | Corrections Issued | JEFFREY PARD |
| Interior/Exterior Lathing | 8/31/2021 | Not Ready for Inspection | JEFFREY PARD |
| PLUMBING-Rough | 8/31/2021 | Corrections Issued | JEFFREY PARD |
| Wood Frame | 8/31/2021 | Not Ready for Inspection | JEFFREY PARD |
| BUILDING-Rough-Frame | 9/7/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| ELECTRICAL-Rough | 9/7/2021 | Approved | DAVID STEPANYAN |
| Green Building Rough | 9/7/2021 | Corrections Issued | DAVID STEPANYAN |
| HVAC-Rough | 9/7/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Interior/Exterior Lathing | 9/7/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| PLUMBING-Rough | 9/7/2021 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 9/20/2021 | Corrections Issued | DAVID STEPANYAN |
| Green Building Rough | 9/20/2021 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 9/20/2021 | Partial Approval | DAVID STEPANYAN |
| Insulation | 9/20/2021 | Partial Approval | DAVID STEPANYAN |
| Interior/Exterior Lathing | 9/20/2021 | Partial Approval | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 9/24/2021 | Approved | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2021 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 9/24/2021 | Approved | DAVID STEPANYAN |
| Insulation | 9/24/2021 | Approved | DAVID STEPANYAN |
| Drywall Nailing | 10/4/2021 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 10/4/2021 | Approved | DAVID STEPANYAN |
| Final | 1/21/2022 | Corrections Issued | TROY SANDERS |
| Green Building Final | 1/21/2022 | Not Ready for Inspection | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 1/21/2022 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 1/21/2022 | Approved | TROY SANDERS |
| Final | 2/14/2022 | Not Ready for Inspection | TROY SANDERS |
| Green Building Final | 2/14/2022 | Approved | TROY SANDERS |
| Final | 2/25/2022 | OK to Issue CofO | TROY SANDERS |