6044-6044 1/2 S 10TH AVE 90043

Certificate Information: 6044-6044 1/2 S 10TH AVE 90043

Application / Permit
21016-20000-14117
Plan Check / Job No.
B21VN06778
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
CONVERT (E) 2-CAR GARAGE ATT. TO (E) DUPLEX TO NEW ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(C); ALL WORK PER WFPP
Permit Issued
Issued on 9/17/2021
Issuing Office
Current Status
CofO Issued on 2/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/3/2021 APPLICANT
Assigned to Plan Check Engineer 6/10/2021 SEAN SHAHMIRI
Corrections Issued 6/15/2021 SEAN SHAHMIRI
Quality Review Completed 6/17/2021 OMID HEDAYAT
Building Plans Picked Up 6/21/2021 APPLICANT
Applicant returned to address corrections 8/24/2021 SEAN SHAHMIRI
Plan Check Approved 9/17/2021 SEAN SHAHMIRI
Issued 9/17/2021 APPLICANT
CofO in Progress 9/12/2022 ENRIQUE MIRELES
Permit Finaled 2/4/2023 DEROLD HAUFF
CofO Issued 2/4/2023 DEROLD HAUFF
Permit Finaled 2/4/2023 DEROLD HAUFF

Permit Application Clearance Information

ZA Case Cleared 6/29/2021 MAXFIELD VERMY
Address approval Cleared 7/1/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 7/1/2021 JEANIE LAM
Sewer availability Cleared 7/1/2021 JEANIE LAM
Tenant Habitability Plan Cleared 9/15/2021 JEFFREY BULL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/30/2022 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 4/4/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 4/8/2022 Not Ready for Inspection ENRIQUE MIRELES
Interior/Exterior Lathing 4/8/2022 Corrections Issued ENRIQUE MIRELES
Interior/Exterior Lathing 4/13/2022 Approved ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 4/13/2022 Approved ENRIQUE MIRELES
Insulation 4/18/2022 Approved ENRIQUE MIRELES
Drywall Nailing 4/22/2022 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 6/13/2022 SGSOV Not Ready ENRIQUE MIRELES
Underground Mechanical 6/15/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Final 6/21/2022 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 6/21/2022 Approved ALEJANDRO DE ARTOLA
HVAC-Final 6/21/2022 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 6/21/2022 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 6/21/2022 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 6/21/2022 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 7/7/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Final 7/7/2022 Approved ENRIQUE MIRELES
Final 7/7/2022 Corrections Issued ENRIQUE MIRELES
HVAC-Final 7/7/2022 Approved ENRIQUE MIRELES
PLUMBING-Final 7/7/2022 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 7/7/2022 SGSOV Approved ENRIQUE MIRELES
Final 8/26/2022 Corrections Issued ENRIQUE MIRELES
Final 9/9/2022 OK to Issue CofO ENRIQUE MIRELES