476 E 49TH ST 90011

Certificate Information: 476 E 49TH ST 90011

Application / Permit
21016-20000-14078
Plan Check / Job No.
B21VN06759
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) 18' x 22' DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 11/30/2021
Issuing Office
Current Status
CofO Issued on 8/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/1/2021 APPLICANT
Assigned to Plan Check Engineer 6/2/2021 ANGELICA DAVE
Corrections Issued 6/2/2021 ANGELICA DAVE
Applicant returned to address corrections 6/17/2021 ANGELICA DAVE
Applicant returned to address corrections 8/4/2021 ANGELICA DAVE
Plan Check Approved 11/19/2021 ANGELICA MARTINEZ
Issued 11/30/2021 APPLICANT
Building Plans Picked Up 12/1/2021 APPLICANT
CofO in Progress 8/3/2022 JOAQUIN GREENOUGH
Permit Finaled 8/20/2022 DEROLD HAUFF
CofO Issued 8/20/2022 DEROLD HAUFF
Permit Finaled 8/20/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/29/2021 JEANIE LAM
Permit Cleared 6/29/2021 JEANIE LAM
Sewer availability Cleared 6/29/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 7/16/2021 JEANIE LAM
Miscellaneous Cleared 7/26/2021 NOAH MCCOY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/12/2022 Corrections Issued JOAQUIN GREENOUGH
Underground Mechanical 1/20/2022 Partial Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 1/25/2022 Partial Approval HORACE FULTZ
Footing/Foundation/Slab 1/28/2022 Corrections Issued HORACE FULTZ
Footing/Foundation/Slab 1/31/2022 Partial Approval JOAQUIN GREENOUGH
Deputy Drilled-In Anchors 2/1/2022 Conditional Approval SHAVONNE ESPINOZA
Footing/Foundation/Slab 2/4/2022 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 2/7/2022 Approved JOAQUIN GREENOUGH
Wood Frame 2/10/2022 Corrections Issued JOAQUIN GREENOUGH
BUILDING-Rough-Frame 3/1/2022 Corrections Issued JOAQUIN GREENOUGH
Green Building Rough 3/1/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 3/10/2022 Approved JOAQUIN GREENOUGH
Green Building Rough 3/10/2022 Corrections Issued JOAQUIN GREENOUGH
Interior/Exterior Lathing 3/16/2022 Partial Approval JOAQUIN GREENOUGH
ELECTRICAL-Rough 4/5/2022 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Rough 4/7/2022 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 4/7/2022 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Rough 4/20/2022 Corrections Issued JOAQUIN GREENOUGH
HVAC-Rough 4/20/2022 Corrections Issued JOAQUIN GREENOUGH
BUILDING-Rough-Frame 5/10/2022 Approved JOAQUIN GREENOUGH
ELECTRICAL-Rough 5/10/2022 Approved JOAQUIN GREENOUGH
Green Building Rough 5/10/2022 Approved JOAQUIN GREENOUGH
HVAC-Rough 5/10/2022 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 5/10/2022 Approved JOAQUIN GREENOUGH
Insulation 5/13/2022 Approved JOAQUIN GREENOUGH
Drywall Nailing 5/17/2022 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 6/30/2022 SGSOV Not Ready JOAQUIN GREENOUGH
Pre-Inspection 7/8/2022 Corrections Issued JOAQUIN GREENOUGH
Final 7/19/2022 Corrections Issued HORACE FULTZ
Green Building Final 7/19/2022 Approved HORACE FULTZ
SGSOV-Seismic Gas S/O Valve 7/19/2022 SGSOV Not Ready HORACE FULTZ
Smoke Detectors 7/19/2022 Approved HORACE FULTZ
Final 7/26/2022 Conditional Approval ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 7/26/2022 SGSOV Approved ALIZAH MAYAGOITIA
Final 8/1/2022 OK to Issue CofO JOAQUIN GREENOUGH