58 E PALOMA AVE 90291
Certificate Information: 58 E PALOMA AVE 90291
- Application / Permit
- 21016-20000-13943
- Plan Check / Job No.
- B21VN06716
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- INTERIOR REMODEL TO (E) DUPLEX TO REMOVE NON-LOAD BEARING PARTITION WALLS FOR (N) KITCHEN, LIVING ROOM, DINING ROOM, BEDROOMS, AND BATHROOMS.
- Permit Issued
- Issued on 6/19/2021
- Issuing Office
- Current Status
- Permit Finaled on 12/2/2021
Permit Application Status History
| Submitted | 5/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2021 | RAPHAEL ROSAS |
| Corrections Issued | 6/2/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 6/4/2021 | APPLICANT |
| Issued | 6/19/2021 | APPLICANT |
| Permit Finaled | 12/2/2021 | RICHARD STEINBACH |
Permit Application Clearance Information
| Sewer availability | Cleared | 6/10/2021 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2021 | ANTHONY MAINEZ |
Contact Information
| Contractor | Clear Vision Construction; Lic. No.: 1054508-B | 2631 GERONIMO DR OXNARD, CA 93033 |
| Contractor | Owner-Builder | , |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/19/2021 | Corrections Issued | JOHNNY MIRANDA |
| Wood Frame | 7/19/2021 | Approved | JOHNNY MIRANDA |
| Final | 7/29/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Gas Test | 7/29/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 7/29/2021 | Corrections Issued | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 7/29/2021 | SGSOV Not Ready | BRENDAN LOONEY |
| Sewer | 7/29/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Smoke Detectors | 7/29/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Gas Test | 8/2/2021 | Partial Approval | BRENDAN LOONEY |
| PLUMBING-Rough | 8/2/2021 | Partial Approval | BRENDAN LOONEY |
| Sewer | 8/2/2021 | Partial Inspection | BRENDAN LOONEY |
| Gas Test | 8/3/2021 | Approved | DANIEL ORRANTE |
| Green Building Rough | 8/3/2021 | Corrections Issued | DANIEL ORRANTE |
| HVAC-Rough | 8/3/2021 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Rough | 8/3/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 8/6/2021 | Not Ready for Inspection | DANIEL ORRANTE |
| Gas Test | 8/9/2021 | Corrections Issued | JOHNNY MIRANDA |
| Sewer | 8/9/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Insulation | 8/12/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Rough | 8/12/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Shower Pan | 8/12/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Rough | 8/23/2021 | Partial Inspection | JUAN VALENZUELA |
| Shower Pan | 8/23/2021 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 11/2/2021 | Corrections Issued | RICHARD STEINBACH |
| Final | 12/2/2021 | Permit Finaled | RICHARD STEINBACH |
| SGSOV-Seismic Gas S/O Valve | 12/2/2021 | SGSOV Approved | RICHARD STEINBACH |
| Smoke Detectors | 12/2/2021 | Approved | RICHARD STEINBACH |