1940 N AVENUE 51 90042
Certificate Information: 1940 N AVENUE 51 90042
- Application / Permit
- 21016-20000-13823
- Plan Check / Job No.
- B21VN06664
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 9' X 18' DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING. NFPA 13D FIRE SPRINKLERS THROUGHOUT.
- Permit Issued
- Issued on 8/26/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/4/2021 | RAPHAEL ROSAS |
| Corrections Issued | 6/5/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 6/9/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 6/14/2022 | APPLICANT |
| Issued | 8/26/2022 | APPLICANT |
| CofO in Progress | 6/3/2024 | CRAIG VAUGHAN |
| CofO Issued | 6/3/2024 | DEROLD HAUFF |
| Permit Finaled | 6/3/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/7/2021 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 12/7/2021 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 12/7/2021 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 12/7/2021 | CINDY QI |
| Sewer availability | Cleared | 12/7/2021 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 12/8/2021 | CINDY QI |
| Grading Pre-Inspection | Cleared | 3/1/2022 | VASIL MIHALEV |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Truong,, Phong Lap; Lic. No.: C70784 | 20493 E CRESTLINE DRIVE WALNUT, CA 91789 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/30/2022 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 1/4/2023 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 2/22/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 2/22/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 2/28/2023 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Rough | 2/28/2023 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Rough | 2/28/2023 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Rough | 4/14/2023 | Partial Approval | CRAIG VAUGHAN |
| Wood Frame | 4/14/2023 | Partial Approval | CRAIG VAUGHAN |
| Insulation | 4/26/2023 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 6/8/2023 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 6/8/2023 | Partial Approval | CRAIG VAUGHAN |
| Shower Pan | 8/3/2023 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 10/26/2023 | Conditional Approval | SCOTT FINNILA |
| Final | 10/26/2023 | Corrections Issued | SCOTT FINNILA |
| Green Building Final | 10/26/2023 | Approved | SCOTT FINNILA |
| Green Building Rough | 10/26/2023 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 10/26/2023 | SGSOV Not Ready | SCOTT FINNILA |
| Smoke Detectors | 10/26/2023 | Approved | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 10/26/2023 | Corrections Issued | SCOTT FINNILA |
| BUILDING-Rough-Frame | 5/10/2024 | Partial Approval | CRAIG VAUGHAN |
| Final | 5/10/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 5/10/2024 | SGSOV Approved | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 5/10/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 5/15/2024 | Approved | CRAIG VAUGHAN |
| Final | 5/15/2024 | Corrections Issued | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 5/15/2024 | Approved | CRAIG VAUGHAN |
| Final | 5/30/2024 | OK to Issue CofO | CRAIG VAUGHAN |