2609 S MANNING AVE 90064
Certificate Information: 2609 S MANNING AVE 90064
- Application / Permit
- 21016-20000-13795
- Plan Check / Job No.
- B21VN06639
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR/EXTERIOR REMODEL TO THE 1ST FLOOR OF THE (E) SINGLE FAMILY DWELLING TO REMODEL KITCHEN & BEDROOMS. RE-FRAME 16'-3" X 23'-11' PORTION OF ROOF.
- Permit Issued
- Issued on 1/27/2022
- Issuing Office
- Current Status
- Issued on 1/27/2022
Permit Application Status History
| Submitted | 5/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/27/2021 | SERGIO MUNIZ |
| Corrections Issued | 5/30/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 6/30/2021 | SERGIO MUNIZ |
| Plan Check Approved | 7/27/2021 | SERGIO MUNIZ |
| Plan Check Approved | 9/1/2021 | SERGIO MUNIZ |
| Building Plans Picked Up | 9/1/2021 | APPLICANT |
| Issued | 1/27/2022 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/11/2021 | BRIAN MILLER |
| Sewer availability | Cleared | 6/14/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/15/2021 | DINAH GARIN |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Owner-Builder | , |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/1/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 9/7/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 9/12/2022 | Partial Approval | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 9/12/2022 | Conditional Approval | JOHN KIDWELL |
| PLUMBING-Rough | 9/12/2022 | Partial Approval | JOHN KIDWELL |
| Wood Frame | 9/22/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Wood Frame | 9/27/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Wood Frame | 10/21/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Special/Order Compliance | 11/3/2022 | Not Ready for Inspection | MICHAEL PELHAM |
| Interior/Exterior Lathing | 11/7/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Wood Frame | 11/7/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 11/10/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 11/10/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Wood Frame | 11/10/2022 | Partial Inspection | OGANES TARAKHCHYAN |
| Wood Frame | 11/28/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 11/29/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 12/5/2022 | Partial Approval | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 1/19/2023 | Not Ready for Inspection | HERBERT GIRON |
| Interior/Exterior Lathing | 1/19/2023 | Not Ready for Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 1/23/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2023 | Corrections Issued | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 1/23/2023 | Partial Approval | CLAYTON GRAHAM |
| Deputy Wood Construction | 1/24/2023 | Conditional Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2023 | Partial Approval | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 2/8/2023 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Rough | 2/8/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 2/8/2023 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Rough | 2/8/2023 | Corrections Issued | HERBERT GIRON |
| Shower Pan | 2/8/2023 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 2/14/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 2/14/2023 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Rough | 2/14/2023 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Rough | 2/14/2023 | Corrections Issued | ASHLEY THOMPSON |
| Shower Pan | 2/14/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 2/16/2023 | Off-Hour Fees Due | |
| HVAC-Rough | 2/16/2023 | Off-Hour Fees Due | |
| PLUMBING-Rough | 2/16/2023 | Off-Hour Fees Due | |
| ELECTRICAL-Rough | 2/17/2023 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 2/17/2023 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Rough | 2/17/2023 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2023 | Partial Approval | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2023 | Partial Approval | CLAYTON GRAHAM |
| Insulation | 2/24/2023 | Approved | CLAYTON GRAHAM |
| Shower Pan | 2/27/2023 | Approved | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2023 | Corrections Issued | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2023 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2023 | Partial Approval | JEREMY TODD |
| Deputy Wood Construction | 4/4/2023 | Conditional Approval | ASHLEY THOMPSON |
| Deputy Wood Construction | 4/5/2023 | Conditional Approval | MICHAEL PELHAM |
| HVAC-Rough | 4/7/2023 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 4/20/2023 | Approved | CLAYTON GRAHAM |