807-807 1/2 S CENTRE ST 90731

Certificate Information: 807-807 1/2 S CENTRE ST 90731

Application / Permit
21016-20000-13793
Plan Check / Job No.
B21VN06635
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 20' X 23' ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e). ALL WORK PER DESIGN.
Permit Issued
Issued on 1/22/2022
Issuing Office
Current Status
CofO Issued on 7/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2021 APPLICANT
Assigned to Plan Check Engineer 6/16/2021 RAPHAEL ROSAS
Corrections Issued 6/17/2021 RAPHAEL ROSAS
Plan Check Approved 12/30/2021 RAPHAEL ROSAS
Issued 1/22/2022 APPLICANT
Building Plans Picked Up 5/4/2022 APPLICANT
CofO in Progress 7/5/2023 ANSON MAGLASANG
Permit Finaled 7/5/2023 ANSON MAGLASANG
CofO Issued 7/5/2023 ANSON MAGLASANG
Permit Finaled 7/5/2023 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 6/18/2021 JOSE HERNANDEZ
Miscellaneous Cleared 6/18/2021 NOAH MCCOY
City Hist. Cultural Monument Cleared 6/21/2021 MICAELA TORRES-GIL
Historic monument Cleared 6/21/2021 MICAELA TORRES-GIL
Eng Process Fee Ord 176,300 Cleared 6/22/2021 JOSE HERNANDEZ
Sewer availability Cleared 6/22/2021 JOSE HERNANDEZ
Redevelopment Project Area Cleared 6/25/2021 GRACIELA ACOSTA
ZI Cleared 6/25/2021 GRACIELA ACOSTA
Tenant Habitability Plan Cleared 10/28/2021 MICHAEL SOTO
"D" conditions Cleared 12/15/2021 NORALI MARTINEZ
Community Plan Implem. Overlay Cleared 12/15/2021 NORALI MARTINEZ
ZI Cleared 12/15/2021 NORALI MARTINEZ

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor N E Construction; Lic. No.: 696948-B 22817 VENTURA BLVD #930      WOODLAND HILLS, CA 91364

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/21/2022 Corrections Issued ANSON MAGLASANG
Underground Mechanical 3/21/2022 Partial Approval ANSON MAGLASANG
Wood Frame 3/21/2022 Not Ready for Inspection ANSON MAGLASANG
BUILDING-Rough-Frame 4/5/2022 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 4/5/2022 Not Ready for Inspection EUGENE CASSIDY
Footing/Foundation/Slab 4/5/2022 Approved EUGENE CASSIDY
Green Building Rough 4/5/2022 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 4/5/2022 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 7/19/2022 Partial Approval ANSON MAGLASANG
PLUMBING-Rough 7/19/2022 Partial Approval ANSON MAGLASANG
Wood Frame 7/19/2022 Partial Approval ANSON MAGLASANG
Floor/Roof Diaphrgm/Shear Wall 8/22/2022 Partial Approval ANSON MAGLASANG
Insulation 8/22/2022 Approved ANSON MAGLASANG
Drywall Nailing 9/7/2022 Approved ANSON MAGLASANG
Interior/Exterior Lathing 9/7/2022 Approved ANSON MAGLASANG
BUILDING-Rough-Frame 12/6/2022 Approved ANSON MAGLASANG
Final 12/6/2022 Corrections Issued ANSON MAGLASANG
Green Building Final 12/6/2022 Approved ANSON MAGLASANG
Green Building Rough 12/6/2022 Approved ANSON MAGLASANG
SGSOV-Seismic Gas S/O Valve 12/6/2022 SGSOV Not Ready ANSON MAGLASANG
Smoke Detectors 12/6/2022 Approved ANSON MAGLASANG
Final 3/2/2023 Corrections Issued ANSON MAGLASANG
SGSOV-Seismic Gas S/O Valve 3/2/2023 SGSOV Not Ready ANSON MAGLASANG
Final 5/9/2023 Corrections Issued JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 5/9/2023 SGSOV Approved JAMES CHAVEZ
Final 5/19/2023 Corrections Issued ANSON MAGLASANG
Final 7/5/2023 OK to Issue CofO ANSON MAGLASANG
Service/Power Release 7/5/2023 Approved ANSON MAGLASANG