650 N LAUREL AVE 90048
Certificate Information: 650 N LAUREL AVE 90048
- Application / Permit
- 21016-20000-13692
- Plan Check / Job No.
- B21VN06580
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18' X 24'-4" DETACHED REC ROOM AND 18' X 20'-2" CARPORT INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 7/11/2021
- Issuing Office
- Current Status
- CofO Issued on 3/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2021 | RAPHAEL ROSAS |
| Corrections Issued | 6/3/2021 | RAPHAEL ROSAS |
| Issued | 7/11/2021 | APPLICANT |
| Building Plans Picked Up | 7/14/2021 | APPLICANT |
| CofO in Progress | 3/1/2023 | MICHAEL LEWIS |
| CofO Issued | 3/15/2023 | DEROLD HAUFF |
| Permit Finaled | 3/15/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/10/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 6/10/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 6/15/2021 | RENZ SORIANO |
Contact Information
| Contractor | La Green Development Inc; Lic. No.: 1061369-B | 15260 VENTURA BLVD 840 SHERMAN OAKS, CA 91403 |
| Engineer | Manlangit,, Vicente Balingasa; Lic. No.: C75499 | 7919 SAUSALITO AVE WEST HILLS, CA 91304 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/23/2021 | Approved | CHRIS CHRISTENSEN |
| Deputy Drilled-In Anchors | 1/5/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 1/5/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 1/7/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 1/11/2022 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 1/27/2022 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 2/4/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Gas Test | 2/25/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 2/25/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 2/25/2022 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 2/25/2022 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 2/28/2022 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 2/28/2022 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 2/28/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| Underground Mechanical | 3/4/2022 | Approved | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 3/8/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 3/10/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Insulation | 3/14/2022 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 3/14/2022 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 3/16/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Rough | 3/16/2022 | Approved | ALIZAH MAYAGOITIA |
| METHANE-Rough | 3/16/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 3/18/2022 | Approved | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2022 | Approved | ARTHUR SARGSYAN |
| METHANE-Rough | 3/18/2022 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 4/5/2022 | Approved | ADAM ESCOTO |
| Interior/Exterior Lathing | 4/5/2022 | Conditional Approval | ADAM ESCOTO |
| Shower Pan | 4/5/2022 | Approved | ADAM ESCOTO |
| Final | 1/17/2023 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 1/17/2023 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 1/17/2023 | SGSOV Not Ready | MICHAEL LEWIS |
| Smoke Detectors | 1/17/2023 | Approved | MICHAEL LEWIS |
| Final | 1/27/2023 | Partial Inspection | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 1/27/2023 | SGSOV Approved | MICHAEL LEWIS |
| Final | 2/14/2023 | Conditional Approval | RUBEN SALAS |
| Final | 3/1/2023 | OK to Issue CofO | MICHAEL LEWIS |