7955 N HASKELL AVE 6-11 91406

Certificate Information: 7955 N HASKELL AVE 6-11 91406

Application / Permit
21016-20000-13667
Plan Check / Job No.
B21VN06565
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(12) Manufacturing
Work Description
FIRE DAMAGE REPAIR UNITS 7 THRU 10. PARKING RESTRIPING TO ADD ACCESSIBLE STALLS SEE COMMENTS
Permit Issued
Issued on 2/24/2022
Issuing Office
Current Status
CofO Issued on 7/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/26/2021 APPLICANT
Assigned to Plan Check Engineer 7/1/2021 MARVEL DELACRUZ
Corrections Issued 7/8/2021 MARVEL DELACRUZ
Quality Review Completed 7/16/2021 STEVEN KIM
Building Plans Picked Up 8/2/2021 APPLICANT
Plan Check Approved 12/6/2021 MARVEL DELACRUZ
Issued 2/24/2022 APPLICANT
CofO in Progress 7/17/2024 KENNETH ROBERTS
Permit Finaled 7/31/2024 JEFFREY DURAN
CofO Issued 7/31/2024 JEFFREY DURAN

Permit Application Clearance Information

DAS Clearance Cleared 10/7/2021 MARVEL DELACRUZ

Contact Information

Contractor Blusky Restoration Contractors Llc; Lic. No.: 1005805-B 9767 E EASTER AVE      CENTENNIAL, CO 80112
Engineer Bayat,, Hooman; Lic. No.: C79761 14813 MORRISON ST      SHERMAN OAKS, CA 91403

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/28/2022 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 6/2/2022 Not Ready for Inspection JEFFREY FULTON
Footing/Foundation/Slab 6/8/2022 Partial Inspection JEFFREY FULTON
Reinforced Concrete Frame 6/22/2022 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 8/4/2022 Not Ready for Inspection JEFFREY FULTON
Deputy Drilled-In Anchors 8/8/2022 Conditional Approval JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 8/29/2022 Partial Inspection JEFFREY FULTON
Drywall Nailing 10/31/2022 No Access for Inspection JEFFREY FULTON
Interior/Exterior Lathing 10/31/2022 No Access for Inspection JEFFREY FULTON
Interior/Exterior Lathing 11/2/2022 Not Ready for Inspection JEFFREY FULTON
Interior/Exterior Lathing 11/7/2022 Approved ANDREW DORSO
Wood Frame 9/19/2023 Partial Inspection DEANDRE HOFFMAN
Footing/Foundation/Slab 10/10/2023 Partial Inspection MARTIN TAVITIAN
Reinforced Concrete Frame 10/10/2023 Partial Inspection MARTIN TAVITIAN
Wood Frame 10/10/2023 Partial Inspection MARTIN TAVITIAN
Footing/Foundation/Slab 10/12/2023 Corrections Issued DEANDRE HOFFMAN
Grading Pre-Inspection 10/12/2023 Not Ready for Inspection DEANDRE HOFFMAN
Masonry Wall/Backfill 10/12/2023 Not Ready for Inspection DEANDRE HOFFMAN
Pre-Inspection 10/12/2023 Not Ready for Inspection DEANDRE HOFFMAN
Reinforced Concrete Frame 10/12/2023 Not Ready for Inspection DEANDRE HOFFMAN
Insulation 11/3/2023 Partial Inspection DEANDRE HOFFMAN
Drywall Nailing 11/9/2023 Approved ANDREW DORSO
Final 6/12/2024 Partial Inspection KENNETH ROBERTS
Green Building Final 6/12/2024 Approved KENNETH ROBERTS
SGSOV-Seismic Gas S/O Valve 6/12/2024 SGSOV Approved KENNETH ROBERTS
Smoke Detectors 6/12/2024 Approved KENNETH ROBERTS
Final 7/11/2024 Partial Approval KENNETH ROBERTS
Final 7/17/2024 OK to Issue CofO KENNETH ROBERTS