11231 N MONTGOMERY AVE 91344

Certificate Information: 11231 N MONTGOMERY AVE 91344

Application / Permit
21016-20000-13613
Plan Check / Job No.
B21VN06533
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion of an existing detached 2-car garage into an Accessory Dwelling Unit per ordinance 186,481.
Permit Issued
Issued on 9/7/2021
Issuing Office
Current Status
CofO Issued on 7/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/25/2021 APPLICANT
Assigned to Plan Check Engineer 5/31/2021 HELEN NGUYEN
Corrections Issued 5/31/2021 HELEN NGUYEN
Applicant returned to address corrections 8/26/2021 HELEN NGUYEN
Plan Check Approved 9/1/2021 HELEN NGUYEN
Issued 9/7/2021 APPLICANT
CofO in Progress 7/28/2022 JAVIER RAMOS JR
Permit Finaled 7/29/2022 DANIEL ORRANTE
CofO Issued 7/29/2022 DANIEL ORRANTE
Permit Finaled 7/29/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/7/2021 CARLOS AGUILERA
Grading Pre-Inspection Cleared 6/7/2021 BRIAN MILLER
Sewer availability Cleared 6/7/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/8/2021 CARLOS AGUILERA
Construction near power lines Cleared 8/10/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/18/2022 Approved MARK JOHNSON
PLUMBING-Rough 1/18/2022 Partial Approval MARK JOHNSON
BUILDING-Rough-Frame 2/18/2022 Corrections Issued MICHAEL TEMPLE
ELECTRICAL-Rough 2/18/2022 Corrections Issued MICHAEL TEMPLE
HVAC-Rough 2/18/2022 Corrections Issued MICHAEL TEMPLE
PLUMBING-Rough 2/18/2022 Corrections Issued MICHAEL TEMPLE
ELECTRICAL-Rough 2/24/2022 Not Ready for Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 2/24/2022 Partial Approval MICHEL ABAJAN
HVAC-Rough 2/24/2022 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 2/24/2022 Not Ready for Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 3/1/2022 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 3/1/2022 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 3/1/2022 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/2/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 3/2/2022 Approved JENNIFER RABUCHIN
Green Building Rough 3/2/2022 Approved JENNIFER RABUCHIN
HVAC-Rough 3/2/2022 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 3/2/2022 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 3/2/2022 Approved JENNIFER RABUCHIN
Insulation 3/7/2022 Approved DEANDRE HOFFMAN
Drywall Nailing 3/17/2022 Corrections Issued JAVIER RAMOS JR
Drywall Nailing 3/22/2022 Approved JAVIER RAMOS JR
Final 5/12/2022 Corrections Issued JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 5/12/2022 SGSOV Not Ready JAVIER RAMOS JR
Smoke Detectors 5/12/2022 Not Ready for Inspection JAVIER RAMOS JR
Final 6/10/2022 Conditional Approval JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 6/10/2022 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 6/10/2022 Approved JAVIER RAMOS JR
ELECTRICAL-Final 7/28/2022 Approved JAVIER RAMOS JR
Final 7/28/2022 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 7/28/2022 Approved JAVIER RAMOS JR
HVAC-Final 7/28/2022 Approved JAVIER RAMOS JR
PLUMBING-Final 7/28/2022 Approved JAVIER RAMOS JR