16917 W RINALDI ST 91344

Certificate Information: 16917 W RINALDI ST 91344

Application / Permit
21016-20000-13575
Plan Check / Job No.
B21VN06526
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EXISTING GARAGE TO BE COVERTED TO A.D.U.
Permit Issued
Issued on 11/3/2021
Issuing Office
Current Status
CofO Issued on 11/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/1/2021 APPLICANT
Assigned to Plan Check Engineer 6/2/2021 JOE VO
Corrections Issued 6/2/2021 JOE VO
Applicant returned to address corrections 6/16/2021 JOE VO
Plan Check Approved 6/19/2021 JOE VO
Issued 11/3/2021 APPLICANT
CofO in Progress 10/2/2023 JAVIER RAMOS JR
Permit Finaled 11/14/2023 RUBEN SALAS
CofO Issued 11/14/2023 RUBEN SALAS
Permit Finaled 11/14/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/4/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 6/4/2021 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 6/4/2021 ADRIAN CASTRO
Sewer availability Cleared 6/4/2021 ADRIAN CASTRO
Construction near power lines Cleared 8/31/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/9/2021 Conditional Approval MICHAEL TEMPLE
Deputy Drilled-In Anchors 11/9/2021 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 11/9/2021 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 11/9/2021 Approved MICHAEL TEMPLE
PLUMBING-Rough 12/2/2021 Approved MARK JOHNSON
Deputy Drilled-In Anchors 12/3/2021 Conditional Approval MARK JOHNSON
Deputy Reinf. Concrete 12/6/2021 Conditional Approval MARK JOHNSON
Footing/Foundation/Slab 12/8/2021 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 2/25/2022 Not Ready for Inspection DEANDRE HOFFMAN
ELECTRICAL-Rough 2/25/2022 Not Ready for Inspection DEANDRE HOFFMAN
Gas Test 2/25/2022 Not Ready for Inspection DEANDRE HOFFMAN
MERV13>=Rough 2/25/2022 Not Ready for Inspection DEANDRE HOFFMAN
PLUMBING-Rough 2/25/2022 Not Ready for Inspection DEANDRE HOFFMAN
BUILDING-Rough-Frame 3/14/2022 No Access for Inspection RAUL OLAGI
ELECTRICAL-Rough 3/14/2022 No Access for Inspection RAUL OLAGI
MERV13>=Rough 3/14/2022 No Access for Inspection RAUL OLAGI
PLUMBING-Rough 3/14/2022 No Access for Inspection RAUL OLAGI
BUILDING-Rough-Frame 6/27/2022 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 6/27/2022 Corrections Issued JAVIER RAMOS JR
MERV13>=Rough 6/27/2022 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Rough 6/27/2022 Corrections Issued JAVIER RAMOS JR
Shower Pan 8/17/2022 Approved JAVIER RAMOS JR
Underground Mechanical 8/17/2022 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 10/11/2022 Approved JAVIER RAMOS JR
Gas Test 10/11/2022 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 10/11/2022 Not Ready for Inspection JAVIER RAMOS JR
Underground Mechanical 10/11/2022 Approved JAVIER RAMOS JR
Gas Test 11/10/2022 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 11/10/2022 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 12/15/2022 Not Ready for Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 12/15/2022 Approved JAVIER RAMOS JR
MERV13>=Rough 12/15/2022 Approved JAVIER RAMOS JR
PLUMBING-Rough 12/15/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 1/20/2023 Not Ready for Inspection JAVIER RAMOS JR
Green Building Rough 1/20/2023 Approved JAVIER RAMOS JR
HVAC-Rough 1/20/2023 Corrections Issued JAVIER RAMOS JR
Insulation 1/20/2023 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 2/16/2023 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 2/16/2023 Approved JAVIER RAMOS JR
HVAC-Rough 2/16/2023 Approved JAVIER RAMOS JR
Insulation 2/16/2023 Approved JAVIER RAMOS JR
Drywall Nailing 2/27/2023 Approved JAVIER RAMOS JR
Final 7/20/2023 Corrections Issued JAVIER RAMOS JR
MERV13>=Final 7/20/2023 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 7/20/2023 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 7/20/2023 Not Ready for Inspection JAVIER RAMOS JR
Final 9/25/2023 OK to Issue CofO JAVIER RAMOS JR
Service/Power Release 9/25/2023 Approved JAVIER RAMOS JR
Smoke Detectors 9/25/2023 Approved JAVIER RAMOS JR