9331-9333 N GOTHIC AVE 91343
Certificate Information: 9331-9333 N GOTHIC AVE 91343
- Application / Permit
- 21016-20000-13503
- Plan Check / Job No.
- B21VN06499
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT (301 SQ FT) PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 9/13/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/31/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/27/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 5/29/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 8/4/2021 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 8/10/2021 | APPLICANT |
| Issued | 9/13/2021 | APPLICANT |
| CofO in Progress | 2/15/2022 | RAUL OLAGI |
| Permit Finaled | 3/31/2022 | DANIEL ORRANTE |
| CofO Issued | 3/31/2022 | DANIEL ORRANTE |
| Permit Finaled | 3/31/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 7/28/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/28/2021 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 8/4/2021 | JEROME MAGAT PALMA |
Contact Information
| Contractor | Mnm Remodeling Inc; Lic. No.: 1003511-B | 6200 CANOGA AVE SUITE 207 WOODLAND HILLS, CA 91367 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 9/20/2021 | Not Ready for Inspection | MARK JOHNSON |
| Green Building Rough | 9/20/2021 | Not Ready for Inspection | MARK JOHNSON |
| PLUMBING-Rough | 9/20/2021 | Partial Approval | MARK JOHNSON |
| Footing/Foundation/Slab | 9/23/2021 | Approved | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 9/24/2021 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 10/7/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2021 | Partial Approval | JACK KARGODORIAN |
| Green Building Rough | 10/7/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Rough | 10/22/2021 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 10/22/2021 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 10/22/2021 | Approved | RAUL OLAGI |
| Sewer | 10/22/2021 | Approved | RAUL OLAGI |
| Underground Mechanical | 10/22/2021 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 10/27/2021 | Partial Approval | RAUL OLAGI |
| ELECTRICAL-Rough | 10/27/2021 | Approved | RAUL OLAGI |
| Green Building Rough | 10/27/2021 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 10/27/2021 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 11/1/2021 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2021 | Approved | RAUL OLAGI |
| Green Building Rough | 11/1/2021 | Approved | RAUL OLAGI |
| Insulation | 11/1/2021 | Corrections Issued | RAUL OLAGI |
| Interior/Exterior Lathing | 11/1/2021 | Approved | RAUL OLAGI |
| Shower Pan | 11/1/2021 | Not Ready for Inspection | RAUL OLAGI |
| Wood Frame | 11/1/2021 | Approved | RAUL OLAGI |
| Insulation | 11/4/2021 | Corrections Issued | RAUL OLAGI |
| Interior/Exterior Lathing | 11/4/2021 | Approved | RAUL OLAGI |
| Shower Pan | 11/4/2021 | Corrections Issued | RAUL OLAGI |
| Insulation | 11/8/2021 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 11/8/2021 | Approved | RAUL OLAGI |
| Shower Pan | 11/8/2021 | Approved | RAUL OLAGI |
| Drywall Nailing | 11/12/2021 | Corrections Issued | ASHLEY THOMPSON |
| Drywall Nailing | 11/18/2021 | Corrections Issued | ALAN MORELOS |
| Drywall Nailing | 11/23/2021 | Approved | ALAN MORELOS |
| ELECTRICAL-Final | 1/14/2022 | Corrections Issued | RAUL OLAGI |
| Final | 1/14/2022 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 1/14/2022 | Corrections Issued | RAUL OLAGI |
| HVAC-Final | 1/14/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 1/14/2022 | Corrections Issued | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 1/14/2022 | SGSOV Not Ready | RAUL OLAGI |
| Smoke Detectors | 1/14/2022 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Final | 2/1/2022 | Approved | RAUL OLAGI |
| Final | 2/1/2022 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 2/1/2022 | Approved | RAUL OLAGI |
| HVAC-Final | 2/1/2022 | Approved | RAUL OLAGI |
| PLUMBING-Final | 2/1/2022 | Corrections Issued | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 2/1/2022 | SGSOV Not Ready | RAUL OLAGI |
| Smoke Detectors | 2/1/2022 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 2/7/2022 | SGSOV Not Ready | RAUL OLAGI |
| Final | 2/10/2022 | OK to Issue CofO | RAUL OLAGI |
| PLUMBING-Final | 2/10/2022 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 2/10/2022 | SGSOV Approved | RAUL OLAGI |