15210-15212 W KITTRIDGE ST 91405

Certificate Information: 15210-15212 W KITTRIDGE ST 91405

Application / Permit
21016-20000-13480
Plan Check / Job No.
B21VN06484
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED 25' X 19' 2-CAR GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 6/25/2021
Issuing Office
Current Status
CofO Issued on 5/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/24/2021 APPLICANT
Assigned to Plan Check Engineer 5/27/2021 GURUNATH NESARAJAH
Corrections Issued 5/30/2021 GURUNATH NESARAJAH
Plan Check Approved 6/22/2021 GURUNATH NESARAJAH
Issued 6/25/2021 APPLICANT
Building Plans Picked Up 7/2/2021 APPLICANT
CofO in Progress 5/18/2023 RYAN SALAZAR
Permit Finaled 5/25/2023 MICHAEL SMITH
CofO Issued 5/25/2023 MICHAEL SMITH
Permit Finaled 5/25/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/9/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 6/9/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 6/9/2021 DAGOVERTO GUERRERO
ZA Case Cleared 6/10/2021 LAUREN PADICK
ZI Cleared 6/10/2021 LAUREN PADICK

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/12/2021 Corrections Issued RICHARD DOCKUS
BUILDING-Rough-Frame 10/19/2021 Not Ready for Inspection RICHARD DOCKUS
Footing/Foundation/Slab 10/19/2021 Approved RICHARD DOCKUS
Green Building Rough 10/19/2021 Not Ready for Inspection RICHARD DOCKUS
PLUMBING-Rough 10/19/2021 Partial Approval RICHARD DOCKUS
ELECTRICAL-Rough 11/3/2021 Approved RICHARD DOCKUS
Green Building Rough 11/3/2021 Not Ready for Inspection RICHARD DOCKUS
Green Building Rough 11/10/2021 Approved RICHARD DOCKUS
Rough-Elec/Plmb/HVAC 11/10/2021 Approved RICHARD DOCKUS
Insulation 11/23/2021 Corrections Issued ALAN MORELOS
Interior/Exterior Lathing 11/23/2021 Partial Approval ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 12/9/2021 No Access for Inspection RICHARD DOCKUS
Insulation 12/9/2021 No Access for Inspection RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 12/15/2021 Approved RICHARD DOCKUS
Insulation 12/15/2021 Corrections Issued RICHARD DOCKUS
BUILDING-Rough-Frame 12/21/2021 Approved RICHARD DOCKUS
Insulation 12/21/2021 Approved RICHARD DOCKUS
Interior/Exterior Lathing 12/28/2021 Approved ALAN MORELOS
Shower Pan 12/28/2021 Approved ALAN MORELOS
Drywall Nailing 12/30/2021 Approved RICHARD DOCKUS
Final 4/19/2022 Corrections Issued MICHAEL TEMPLE
Green Building Final 4/19/2022 Not Ready for Inspection MICHAEL TEMPLE
SGSOV-Seismic Gas S/O Valve 4/19/2022 SGSOV Not Ready MICHAEL TEMPLE
Smoke Detectors 4/19/2022 Approved MICHAEL TEMPLE
Final 5/4/2022 Not Ready for Inspection RICHARD DOCKUS
Green Building Final 5/4/2022 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 5/4/2022 SGSOV Approved RICHARD DOCKUS
Final 8/29/2022 No Access for Inspection RICHARD DOCKUS
Final 1/19/2023 Corrections Issued JOHN COLEMAN
Final 5/16/2023 OK to Issue CofO RYAN SALAZAR