20332-20334 W AETNA ST 91367
Certificate Information: 20332-20334 W AETNA ST 91367
- Application / Permit
- 21016-20000-13442
- Plan Check / Job No.
- B21VN06470
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- E-PLAN 1. Conversion of Garage into Junior Accessory Dwelling Unit per GCS65852.2(e)(1)(A) and 65852.22 2. NEW CONCRETE STAIR FROM CURB TO ADU ENTRANCE "COMPLY WITH DEPARTMENT ORDER effective date 02/08/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". All permits shall be for the same time period limitation. CEIS Case Number is 839601.
- Permit Issued
- Issued on 9/13/2021
- Issuing Office
- Current Status
- Issued on 9/13/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/1/2021 | ZAW HAN |
| Corrections Issued | 6/1/2021 | ZAW HAN |
| Applicant returned to address corrections | 8/17/2021 | ZAW HAN |
| Plan Check Approved | 9/2/2021 | ZAW HAN |
| Issued | 9/13/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/7/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 6/7/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/7/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/10/2021 | CARLOS AGUILERA |
| ZA Case | Cleared | 8/3/2021 | PABLO ESTRADA |
Contact Information
| Architect | Walker,, Cory; Lic. No.: C37193 | 3734 DELMAS TERRACE, APT 14 LOS ANGELES, CA 90034 |
| Contractor | Owner-Builder | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| FELIPE PENICHE, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/14/2021 | Approved | RICHARD SIMONS |
| Footing/Foundation/Slab | 10/18/2021 | Approved | EMIL ALEXANDRIAN |
| PLUMBING-Rough | 10/18/2021 | Not Ready for Inspection | EMIL ALEXANDRIAN |
| Underground Mechanical | 10/18/2021 | Approved | EMIL ALEXANDRIAN |
| Insulation | 11/16/2021 | Partial Approval | RICHARD SIMONS |
| Wood Frame | 11/18/2021 | Approved | RICHARD SIMONS |
| Rough-Elec/Plmb/HVAC | 3/18/2022 | Approved | RICHARD SIMONS |
| Insulation | 3/30/2022 | Approved | RICHARD SIMONS |
| Drywall Nailing | 4/5/2022 | Approved | EMIL ALEXANDRIAN |
| Interior/Exterior Lathing | 4/5/2022 | Approved | EMIL ALEXANDRIAN |
| Pre-Inspection | 12/7/2023 | Corrections Issued | ROBERT SUNSERI |
| BUILDING-Rough-Frame | 1/17/2024 | No Access for Inspection | ARA SINANIAN |
| Final | 1/17/2024 | Not Ready for Inspection | ARA SINANIAN |
| Green Building Final | 1/17/2024 | Not Ready for Inspection | ARA SINANIAN |
| Green Building Rough | 1/17/2024 | Not Ready for Inspection | ARA SINANIAN |
| SGSOV-Seismic Gas S/O Valve | 1/17/2024 | SGSOV Not Ready | ARA SINANIAN |
| Smoke Detectors | 1/17/2024 | Not Ready for Inspection | ARA SINANIAN |