17403 W KESWICK ST 91325
Certificate Information: 17403 W KESWICK ST 91325
- Application / Permit
- 21016-20000-13294
- Plan Check / Job No.
- B21VN06367
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20'-5" X 20'-7" DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 7/30/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/15/2021 | RAPHAEL ROSAS |
| Corrections Issued | 6/15/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 7/27/2021 | APPLICANT |
| Issued | 7/30/2021 | APPLICANT |
| CofO in Progress | 2/1/2022 | RAUL OLAGI |
| Permit Finaled | 2/12/2022 | MICHAEL SMITH |
| CofO Issued | 2/12/2022 | MICHAEL SMITH |
| Permit Finaled | 2/12/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 6/21/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/21/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/22/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Amerbuild Inc; Lic. No.: 1024554-B | 22108 VANOWEN STREET WOODLAND HILLS, CA 91303 |
| Engineer | Terrio,, Greyson Franklin; Lic. No.: C87383 | 22647 VENTURA BLVD 362 WOODLAND HILLS, CA 91364 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Test | 9/3/2021 | Partial Approval | AMY COLIN |
| PLUMBING-Rough | 9/3/2021 | Partial Approval | AMY COLIN |
| Sewer | 9/3/2021 | Approved | AMY COLIN |
| Deputy Drilled-In Anchors | 9/10/2021 | Conditional Approval | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 9/14/2021 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 10/18/2021 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 10/18/2021 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 10/18/2021 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 10/18/2021 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 10/21/2021 | Partial Approval | RAUL OLAGI |
| ELECTRICAL-Rough | 10/21/2021 | Approved | RAUL OLAGI |
| Green Building Rough | 10/21/2021 | Approved | RAUL OLAGI |
| HVAC-Rough | 10/21/2021 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 10/21/2021 | Approved | RAUL OLAGI |
| Insulation | 11/4/2021 | Corrections Issued | RAUL OLAGI |
| Interior/Exterior Lathing | 11/4/2021 | Approved | RAUL OLAGI |
| Shower Pan | 11/4/2021 | Corrections Issued | RAUL OLAGI |
| Insulation | 11/9/2021 | Approved | RAUL OLAGI |
| Shower Pan | 11/9/2021 | Approved | RAUL OLAGI |
| Drywall Nailing | 11/16/2021 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 11/16/2021 | Approved | ALAN MORELOS |
| SGSOV-Seismic Gas S/O Valve | 1/14/2022 | SGSOV Not Ready | RAUL OLAGI |
| BUILDING-Rough-Frame | 1/24/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 1/24/2022 | Corrections Issued | RAUL OLAGI |
| Final | 1/24/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 1/24/2022 | Corrections Issued | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 1/24/2022 | SGSOV Not Ready | RAUL OLAGI |
| Smoke Detectors | 1/24/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 1/31/2022 | Approved | RAUL OLAGI |
| Final | 1/31/2022 | Corrections Issued | RAUL OLAGI |
| HVAC-Final | 1/31/2022 | Approved | RAUL OLAGI |
| PLUMBING-Final | 1/31/2022 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 1/31/2022 | SGSOV Approved | RAUL OLAGI |
| Final | 2/1/2022 | OK to Issue CofO | RAUL OLAGI |