3720 S MIDVALE AVE 1-8 90034
Certificate Information: 3720 S MIDVALE AVE 1-8 90034
- Application / Permit
- 21016-20000-13201
- Plan Check / Job No.
- B21VN06320
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- COVERT UNIT #1 (2 BEDROOM) INTO 2 SEPARATE STUDIO (NO BEDROOMS) UNITS
- Permit Issued
- Issued on 10/13/2021
- Issuing Office
- Current Status
- CofO Corrected on 10/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2021 | MARVEL DELACRUZ |
| Corrections Issued | 6/5/2021 | MARVEL DELACRUZ |
| Quality Review Completed | 6/10/2021 | STEVEN KIM |
| Building Plans Picked Up | 6/11/2021 | APPLICANT |
| Applicant returned to address corrections | 8/25/2021 | MARVEL DELACRUZ |
| Plan Check Approved | 10/13/2021 | MARVEL DELACRUZ |
| Issued | 10/13/2021 | APPLICANT |
| CofO in Progress | 9/22/2022 | GRANT WOODS |
| CofO Issued-Status Void | 9/29/2022 | DAVID TSAU |
| Permit Finaled-Status Void | 9/29/2022 | DAVID TSAU |
| Re-Activate Permit | 10/4/2022 | DAVID TSAU |
| Permit Finaled | 10/4/2022 | DAVID TSAU |
| CofO Corrected | 10/4/2022 | DAVID TSAU |
| Permit Finaled | 10/4/2022 | DAVID TSAU |
Permit Application Clearance Information
| Address approval | Cleared | 6/22/2021 | DINAH GARIN |
| Sewer availability | Cleared | 6/22/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/23/2021 | DINAH GARIN |
| Specific Plan | Cleared | 8/26/2021 | PEDRO AYALA |
| Tenant Habitability Plan | Cleared | 9/29/2021 | MICHAEL SOTO |
| ZI | Cleared | 10/1/2021 | PABLO ESTRADA |
Contact Information
| Architect | Nigosian,, Michael Nickolas; Lic. No.: C35308 | 75-572 PAINTED DESERT DRIVE INDIAN WELLS, CA 92210 |
| Contractor | Owner-Builder | , |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Insulation | 3/10/2022 | Partial Approval | JOHN DODGE |
| Wood Frame | 3/10/2022 | Partial Approval | JOHN DODGE |
| Wood Frame | 3/23/2022 | Approved | JOHN DODGE |
| Interior/Exterior Lathing | 3/25/2022 | Approved | JEFF BYTHEWAY |
| Wood Frame | 3/25/2022 | Not Ready for Inspection | JEFF BYTHEWAY |
| Wood Frame | 3/30/2022 | Conditional Approval | JOHN DODGE |
| Insulation | 4/4/2022 | Approved | JOHN DODGE |
| Drywall Nailing | 4/8/2022 | Approved | JOHN DODGE |
| Interior/Exterior Lathing | 5/2/2022 | Approved | PAUL DAVIDSON |
| Final | 9/2/2022 | Not Ready for Inspection | PAUL DAVIDSON |
| SGSOV-Seismic Gas S/O Valve | 9/2/2022 | SGSOV Approved | PAUL DAVIDSON |
| Smoke Detectors | 9/2/2022 | Approved | PAUL DAVIDSON |
| Final | 9/9/2022 | Conditional Approval | GRANT WOODS |