7523-7525 S DENROCK AVE 90045
Certificate Information: 7523-7525 S DENROCK AVE 90045
- Application / Permit
- 21016-20000-13091
- Plan Check / Job No.
- B21VN06256
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED 20' 2" X 20' DEN TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 11/29/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 6/4/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 10/19/2021 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 10/22/2021 | APPLICANT |
| Issued | 11/29/2021 | APPLICANT |
| CofO in Progress | 6/21/2022 | BOBBY KEY |
| Permit Finaled | 7/6/2022 | DANIEL ORRANTE |
| CofO Issued | 7/6/2022 | DANIEL ORRANTE |
| Permit Finaled | 7/6/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/23/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 8/23/2021 | ANTHONY MAINEZ |
| ZI | Cleared | 8/24/2021 | DANG NGUYEN |
| Specific Plan | Cleared | 8/26/2021 | PETE EYRE |
| Grading Pre-Inspection | Cleared | 8/30/2021 | VASIL MIHALEV |
| Eng Process Fee Ord 176,300 | Cleared | 9/20/2021 | ANTHONY MAINEZ |
Contact Information
| Contractor | Azure Construction Inc; Lic. No.: 1058246-B | 3877 GRAND VIEW BLVD STE 200 LOS ANGELES, CA 90066 |
| Engineer | Dominguez,, Refugio; Lic. No.: C50820 | 254 COTTONWOOD ST ONTARIO, CA 91761 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/14/2021 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 12/22/2021 | Approved | BOBBY KEY |
| Final | 12/22/2021 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 12/22/2021 | Approved | BOBBY KEY |
| Gas Test | 1/12/2022 | Approved | BOBBY KEY |
| Insulation | 1/12/2022 | Approved | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 1/24/2022 | Conditional Approval | BOBBY KEY |
| MERV13>=Rough | 1/24/2022 | Approved | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 2/4/2022 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 2/4/2022 | Approved | BOBBY KEY |
| Insulation | 2/4/2022 | Corrections Issued | BOBBY KEY |
| Insulation | 2/11/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 2/16/2022 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2022 | Approved | BOBBY KEY |
| Green Building Rough | 2/16/2022 | Approved | BOBBY KEY |
| HVAC-Rough | 2/16/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 2/24/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 2/24/2022 | Approved | BOBBY KEY |
| Final | 2/24/2022 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 2/24/2022 | Partial Approval | BOBBY KEY |
| Shower Pan | 3/3/2022 | Approved | CLAYTON GRAHAM |
| Green Building Rough | 3/22/2022 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 3/22/2022 | SGSOV Not Ready | BOBBY KEY |
| Interior/Exterior Lathing | 4/6/2022 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 6/9/2022 | Approved | BOBBY KEY |
| Green Building Final | 6/9/2022 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 6/9/2022 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 6/9/2022 | Approved | BOBBY KEY |
| Final | 6/13/2022 | Corrections Issued | BOBBY KEY |
| Gas Test | 6/13/2022 | Approved | BOBBY KEY |
| HVAC-Final | 6/13/2022 | Approved | BOBBY KEY |
| PLUMBING-Final | 6/13/2022 | Approved | BOBBY KEY |
| Final | 6/21/2022 | OK to Issue CofO | BOBBY KEY |