8010 S EL MANOR AVE 90045
Certificate Information: 8010 S EL MANOR AVE 90045
- Application / Permit
- 21016-20000-13085
- Plan Check / Job No.
- B21VN06253
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20'-0" x 20'-2" DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A).
- Permit Issued
- Issued on 7/7/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2021 | SARKIS HARABEDIAN |
| Corrections Issued | 5/20/2021 | SARKIS HARABEDIAN |
| Plan Check Approved | 6/24/2021 | SARKIS HARABEDIAN |
| Building Plans Picked Up | 6/24/2021 | APPLICANT |
| Issued | 7/7/2021 | APPLICANT |
| CofO in Progress | 11/20/2023 | BOBBY KEY |
| Permit Finaled | 11/21/2023 | DANIEL ORRANTE |
| CofO Issued | 11/21/2023 | DANIEL ORRANTE |
| Permit Finaled | 11/21/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 5/20/2021 | OSCAR CASTRO |
| Address approval | Cleared | 6/14/2021 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2021 | DENNIS BRAGIN |
| Sewer availability | Cleared | 6/14/2021 | DENNIS BRAGIN |
Contact Information
| Architect | Gemigniani,, Richard Louis; Lic. No.: C18783 | 14263 VALLEY VISTA BLVD. SHERMAN OAKS, CA 91403 |
| Contractor | Todd Lance Construction Inc; Lic. No.: 692325-B | 3087 RENEE CT SIMI VALLEY, CA 93065 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 7/14/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 7/14/2021 | Partial Approval | JOHNNY MIRANDA |
| Sewer | 7/14/2021 | Approved | JOHNNY MIRANDA |
| Underground Mechanical | 7/14/2021 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 7/15/2021 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Rough | 7/27/2021 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 7/27/2021 | Approved | ENRIQUE MIRELES |
| Wood Frame | 7/27/2021 | Approved | ENRIQUE MIRELES |
| Insulation | 8/13/2021 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Shower Pan | 8/13/2021 | Approved | SHAVONNE ESPINOZA |
| Insulation | 8/17/2021 | Approved | MORRIS JACKSON |
| Drywall Nailing | 8/20/2021 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Rough | 8/20/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Drywall Nailing | 8/25/2021 | Approved | BRENDAN LOONEY |
| Green Building Rough | 8/25/2021 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 8/25/2021 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 9/3/2021 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 11/2/2022 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 11/2/2022 | Corrections Issued | HERBERT GIRON |
| Final | 11/2/2022 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 11/2/2022 | Approved | HERBERT GIRON |
| HVAC-Final | 11/2/2022 | Corrections Issued | HERBERT GIRON |
| METHANE-Final | 11/2/2022 | Approved | HERBERT GIRON |
| METHANE-Rough | 11/2/2022 | Approved | HERBERT GIRON |
| PLUMBING-Final | 11/2/2022 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 11/2/2022 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 11/2/2022 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 9/13/2023 | Approved | BOBBY KEY |
| Final | 9/13/2023 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Final | 9/13/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 9/13/2023 | Approved | BOBBY KEY |
| Final | 11/20/2023 | OK to Issue CofO | BOBBY KEY |