1707 S DURANGO AVE 90035

Certificate Information: 1707 S DURANGO AVE 90035

Application / Permit
21016-20000-12983
Plan Check / Job No.
B21VN06228
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 19'-6" x 24'-8" DET. GARAGE TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g); AUTOMATIC SPRINKLER SYSTEM IS REQUIRED
Permit Issued
Issued on 9/27/2021
Issuing Office
Current Status
CofO Issued on 3/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/19/2021 APPLICANT
Assigned to Plan Check Engineer 6/3/2021 SEAN SHAHMIRI
Corrections Issued 6/5/2021 SEAN SHAHMIRI
Quality Review Completed 6/7/2021 OMID HEDAYAT
Building Plans Picked Up 6/18/2021 APPLICANT
Applicant returned to address corrections 8/2/2021 SEAN SHAHMIRI
Applicant returned to address corrections 8/26/2021 SEAN SHAHMIRI
Applicant returned to address corrections 9/15/2021 SEAN SHAHMIRI
Plan Check Approved 9/27/2021 SEAN SHAHMIRI
Issued 9/27/2021 APPLICANT
CofO in Progress 3/13/2023 JEREMY TODD
Permit Finaled 3/15/2023 DANIEL ORRANTE
CofO Issued 3/15/2023 DANIEL ORRANTE
Permit Finaled 3/15/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/22/2021 THOMAS LANG
Sewer availability Cleared 7/22/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 9/2/2021 THOMAS LANG
Low Impact Development Cleared 9/14/2021 SARAH YOUSSEF
Grading Pre-Inspection Cleared 9/15/2021 SEAN SHAHMIRI
Roof/Waste drainage to street Cleared 9/21/2021 THAN WIN

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21500 WYANDOTTE ST 106      CANOGA PARK, CA 91303

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/4/2021 Partial Approval EVAN COOPER
Sewer 11/4/2021 Not Ready for Inspection EVAN COOPER
Underground Mechanical 11/4/2021 Partial Approval EVAN COOPER
Deputy Drilled-In Anchors 12/2/2021 Conditional Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 12/3/2021 Approved EVAN COOPER
Footing/Foundation/Slab 12/3/2021 Approved EVAN COOPER
METHANE-Subgrade 12/3/2021 Approved EVAN COOPER
Deputy Reinf. Concrete 12/6/2021 Conditional Approval EVAN COOPER
Deputy Steel/Welding 2/7/2022 Conditional Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 3/7/2022 Approved EVAN COOPER
PLUMBING-Rough 3/30/2022 Partial Inspection KEVIN SARGSYAN
HVAC-Rough 4/6/2022 Corrections Issued EVAN COOPER
METHANE-Rough 4/6/2022 Approved EVAN COOPER
PLUMBING-Rough 4/6/2022 Approved EVAN COOPER
ELECTRICAL-Rough 5/2/2022 Approved EVAN COOPER
HVAC-Rough 5/2/2022 Approved EVAN COOPER
Shower Pan 5/2/2022 Approved EVAN COOPER
Deputy Wood Construction 5/9/2022 Conditional Approval EVAN COOPER
BUILDING-Rough-Frame 5/17/2022 Conditional Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 5/17/2022 Approved EVAN COOPER
Green Building Rough 5/17/2022 Not Ready for Inspection EVAN COOPER
Interior/Exterior Lathing 5/17/2022 Partial Approval EVAN COOPER
Interior/Exterior Lathing 5/23/2022 Approved EVAN COOPER
Insulation 7/1/2022 Corrections Issued EVAN COOPER
Drywall Nailing 7/8/2022 Approved EVAN COOPER
Green Building Rough 7/8/2022 Approved EVAN COOPER
BUILDING-Rough-Frame 3/1/2023 Approved JEREMY TODD
Final 3/1/2023 Corrections Issued JEREMY TODD
Green Building Final 3/1/2023 Approved JEREMY TODD
SGSOV-Seismic Gas S/O Valve 3/1/2023 SGSOV Approved JEREMY TODD
Smoke Detectors 3/1/2023 Approved JEREMY TODD
Final 3/10/2023 OK to Issue CofO JEREMY TODD