7840 S DALTON AVE 90047
Certificate Information: 7840 S DALTON AVE 90047
- Application / Permit
- 21016-20000-12979
- Plan Check / Job No.
- B21VN06224
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 17'-11" X 18' DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 7/20/2021
- Issuing Office
- Current Status
- CofO Issued on 12/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | RAPHAEL ROSAS |
| Corrections Issued | 5/26/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 6/2/2021 | APPLICANT |
| Issued | 7/20/2021 | APPLICANT |
| CofO in Progress | 12/8/2022 | LILIANA PORTILLO |
| Permit Finaled | 12/22/2022 | DEROLD HAUFF |
| CofO Issued | 12/22/2022 | DEROLD HAUFF |
| Permit Finaled | 12/22/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/12/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 7/12/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 7/12/2021 | RENZ SORIANO |
Contact Information
| Contractor | Hi-Tech Builders Inc; Lic. No.: 957111-B | 5435 BALBOA BLVD STE 200 ENCINO, CA 91316 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/27/2021 | Approved | ALEJANDRO DE ARTOLA |
| Deputy Drilled-In Anchors | 8/12/2021 | Approved | WILLIAM WREN |
| Footing/Foundation/Slab | 8/12/2021 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 8/16/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 8/23/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 9/22/2021 | Not Ready for Inspection | DAVID FEILER |
| Underground Mechanical | 9/22/2021 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 9/28/2021 | Corrections Issued | HORACE FULTZ |
| Underground Mechanical | 9/28/2021 | Not Ready for Inspection | HORACE FULTZ |
| PLUMBING-Rough | 9/30/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Underground Mechanical | 9/30/2021 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Rough | 10/5/2021 | Partial Approval | FREDDIE RIVERA |
| Underground Mechanical | 10/5/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 10/20/2021 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 1/4/2022 | Not Ready for Inspection | ADAM ESCOTO |
| ELECTRICAL-Rough | 1/4/2022 | Conditional Approval | ADAM ESCOTO |
| Green Building Rough | 1/4/2022 | Not Ready for Inspection | ADAM ESCOTO |
| PLUMBING-Rough | 1/4/2022 | Corrections Issued | ADAM ESCOTO |
| ELECTRICAL-Rough | 1/6/2022 | Approved | ADAM ESCOTO |
| HVAC-Rough | 1/6/2022 | Conditional Approval | ADAM ESCOTO |
| BUILDING-Rough-Frame | 1/12/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Rough | 1/12/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 1/12/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Rough-Elec/Plmb/HVAC | 1/12/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 1/26/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Rough | 1/26/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Rough | 1/26/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 1/26/2022 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 1/31/2022 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 2/4/2022 | Partial Approval | LILIANA PORTILLO |
| Green Building Rough | 2/4/2022 | Corrections Issued | LILIANA PORTILLO |
| Green Building Rough | 2/11/2022 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 2/11/2022 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 2/11/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 2/16/2022 | Conditional Approval | LILIANA PORTILLO |
| Drywall Nailing | 2/24/2022 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 2/24/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 8/1/2022 | Corrections Issued | LILIANA PORTILLO |
| Final | 8/1/2022 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 8/1/2022 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Final | 8/1/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Final | 8/1/2022 | Corrections Issued | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 8/1/2022 | SGSOV Not Ready | LILIANA PORTILLO |
| Smoke Detectors | 8/1/2022 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 9/14/2022 | SGSOV Not Ready | LILIANA PORTILLO |
| ELECTRICAL-Final | 9/16/2022 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Final | 9/16/2022 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Final | 9/16/2022 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 9/22/2022 | Not Ready for Inspection | HORACE FULTZ |
| ELECTRICAL-Final | 9/22/2022 | Corrections Issued | HORACE FULTZ |
| Final | 9/22/2022 | Not Ready for Inspection | HORACE FULTZ |
| Green Building Final | 9/22/2022 | Not Ready for Inspection | HORACE FULTZ |
| Green Building Rough | 9/22/2022 | Not Ready for Inspection | HORACE FULTZ |
| HVAC-Final | 9/22/2022 | Not Ready for Inspection | HORACE FULTZ |
| PLUMBING-Final | 9/22/2022 | Approved | HORACE FULTZ |
| SGSOV-Seismic Gas S/O Valve | 9/22/2022 | SGSOV Approved | HORACE FULTZ |
| BUILDING-Rough-Frame | 9/28/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 9/28/2022 | Approved | LILIANA PORTILLO |
| Final | 9/28/2022 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 9/28/2022 | Corrections Issued | LILIANA PORTILLO |
| Green Building Rough | 9/28/2022 | Approved | LILIANA PORTILLO |
| HVAC-Final | 9/28/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 11/8/2022 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 11/8/2022 | Approved | LILIANA PORTILLO |
| HVAC-Final | 11/8/2022 | Approved | LILIANA PORTILLO |
| Service/Power Release | 11/8/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Final | 12/7/2022 | Approved | LILIANA PORTILLO |
| Final | 12/7/2022 | OK to Issue CofO | LILIANA PORTILLO |
| Service/Power Release | 12/7/2022 | Approved | LILIANA PORTILLO |