11700 N WOODLEY AVE 91344

Certificate Information: 11700 N WOODLEY AVE 91344

Application / Permit
21016-20000-12965
Plan Check / Job No.
B21VN06213
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL TO (E) ONE STORY SFD AND STRUCTURAL UPGRADE PER ENGINEERED PLANS.
Permit Issued
Issued on 7/2/2021
Issuing Office
Current Status
Permit Finaled on 4/27/2022

Permit Application Status History

Submitted 5/18/2021 APPLICANT
Assigned to Plan Check Engineer 5/21/2021 DAWN MC NULTY
Corrections Issued 5/24/2021 DAWN MC NULTY
Building Plans Picked Up 5/27/2021 APPLICANT
Plan Check Approved 7/2/2021 DAWN MC NULTY
Issued 7/2/2021 APPLICANT
Permit Finaled 4/26/2022 MICHAEL TEMPLE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/2/2021 DAWN MC NULTY

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/16/2021 Approved MARK JOHNSON
Footing/Foundation/Slab 7/16/2021 Approved MARK JOHNSON
ELECTRICAL-Rough 8/27/2021 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 8/27/2021 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 8/27/2021 Not Ready for Inspection MISAEL ESPARZA
Deputy Drilled-In Anchors 8/31/2021 No Access for Inspection MARK JOHNSON
ELECTRICAL-Rough 9/2/2021 Approved MARK JOHNSON
PLUMBING-Rough 9/2/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 9/10/2021 Partial Approval MARK JOHNSON
HVAC-Rough 9/10/2021 Not Ready for Inspection MARK JOHNSON
Insulation 9/14/2021 Partial Approval MARK JOHNSON
BUILDING-Rough-Frame 9/16/2021 Approved MARK JOHNSON
Insulation 9/20/2021 Approved MARK JOHNSON
Drywall Nailing 9/24/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 10/7/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 10/19/2021 Approved MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 3/29/2022 SGSOV Not Ready JAVIER RAMOS JR
Pre-Inspection 4/4/2022 Partial Inspection JAVIER RAMOS JR
Final 4/13/2022 Partial Approval JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 4/13/2022 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 4/13/2022 Approved JAVIER RAMOS JR
Final 4/26/2022 Permit Finaled MICHAEL TEMPLE