5153 1/3-1/2 N CARTWRIGHT AVE 91601
Certificate Information: 5153 1/3-1/2 N CARTWRIGHT AVE 91601
- Application / Permit
- 21016-20000-12876
- Plan Check / Job No.
- B21VN06147
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED ALQ AND GARAGE TO (2) ACCESSORY DWELLING UNITS PER GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 8/3/2021
- Issuing Office
- Current Status
- CofO Issued on 3/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | RAPHAEL ROSAS |
| Corrections Issued | 5/29/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 7/20/2021 | RAPHAEL ROSAS |
| Issued | 8/3/2021 | APPLICANT |
| Building Plans Picked Up | 8/4/2021 | APPLICANT |
| CofO in Progress | 1/17/2024 | JOHN HAYES |
| CofO Issued | 3/18/2024 | RUBEN SALAS |
| Permit Finaled | 3/18/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Hold | Cleared | 6/7/2021 | JASON SHEETS |
| Address approval | Cleared | 7/6/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 7/6/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 7/27/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Dh Remodel Services; Lic. No.: 1030925-B | 5850 W 3RD STREET #160 LOS ANGELES, CA 90036 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 1/19/2022 | Not Ready for Inspection | CALEB MEISTER |
| Footing/Foundation/Slab | 1/19/2022 | Corrections Issued | CALEB MEISTER |
| Green Building Rough | 1/19/2022 | Not Ready for Inspection | CALEB MEISTER |
| Sewer | 1/19/2022 | Corrections Issued | CALEB MEISTER |
| Footing/Foundation/Slab | 2/2/2022 | No Access for Inspection | CHRISTOPHE COCHRAN |
| Deputy Drilled-In Anchors | 2/25/2022 | No Result Entered | RAYMOND KEHOE |
| Footing/Foundation/Slab | 3/1/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 3/1/2022 | Partial Approval | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 3/4/2022 | Conditional Approval | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 3/7/2022 | Corrections Issued | JACK KARGODORIAN |
| Sewer | 3/8/2022 | Corrections Issued | DAVID MATSON |
| Footing/Foundation/Slab | 3/14/2022 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Rough | 3/15/2022 | Partial Approval | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 3/15/2022 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 3/18/2022 | No Access for Inspection | CALEB MEISTER |
| PLUMBING-Rough | 3/18/2022 | No Access for Inspection | CALEB MEISTER |
| HVAC-Rough | 4/8/2022 | Approved | MATT KELLERMAN |
| ELECTRICAL-Rough | 5/16/2022 | Corrections Issued | CALEB MEISTER |
| BUILDING-Rough-Frame | 5/25/2022 | Not Ready for Inspection | ARAM AVEDISIAN |
| Rough-Elec/Plmb/HVAC | 5/25/2022 | Corrections Issued | ARAM AVEDISIAN |
| Wood Frame | 5/27/2022 | Corrections Issued | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 7/27/2022 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 7/27/2022 | Approved | JOHN HAYES |
| Green Building Rough | 7/27/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 7/27/2022 | Approved | JOHN HAYES |
| Pre-Inspection | 7/27/2022 | Approved | JOHN HAYES |
| Sewer | 7/27/2022 | Approved | JOHN HAYES |
| Wood Frame | 7/27/2022 | Partial Approval | JOHN HAYES |
| ELECTRICAL-Rough | 8/2/2022 | Not Ready for Inspection | CALEB MEISTER |
| HVAC-Rough | 8/2/2022 | Not Ready for Inspection | CALEB MEISTER |
| PLUMBING-Rough | 8/2/2022 | Not Ready for Inspection | CALEB MEISTER |
| ELECTRICAL-Rough | 8/4/2022 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Insulation | 8/4/2022 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 8/4/2022 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Insulation | 8/10/2022 | Corrections Issued | CALEB MEISTER |
| BUILDING-Rough-Frame | 8/17/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 8/17/2022 | Not Ready for Inspection | JOHN HAYES |
| Interior/Exterior Lathing | 8/17/2022 | Not Ready for Inspection | JOHN HAYES |
| Insulation | 8/22/2022 | Not Ready for Inspection | CALEB MEISTER |
| Interior/Exterior Lathing | 8/22/2022 | Not Ready for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 8/26/2022 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 8/26/2022 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 8/26/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 9/7/2022 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 9/7/2022 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 9/7/2022 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 9/8/2022 | Off-Hour Fees Due | |
| Wood Frame | 9/9/2022 | Corrections Issued | JOHN HAYES |
| BUILDING-Rough-Frame | 9/15/2022 | Approved | JOHN HAYES |
| Green Building Rough | 9/15/2022 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 9/15/2022 | Approved | JOHN HAYES |
| Wood Frame | 9/15/2022 | Approved | JOHN HAYES |
| Deputy Wood Construction | 9/16/2022 | Conditional Approval | MATT KELLERMAN |
| Insulation | 9/22/2022 | Approved | ALAN MORELOS |
| Drywall Nailing | 9/27/2022 | Not Ready for Inspection | JOHN HAYES |
| Interior/Exterior Lathing | 9/27/2022 | Partial Approval | JOHN HAYES |
| Drywall Nailing | 9/30/2022 | Approved | ALAN MORELOS |
| ELECTRICAL-Final | 2/13/2023 | No Access for Inspection | JOHN HAYES |
| Final | 2/13/2023 | No Access for Inspection | JOHN HAYES |
| Green Building Final | 2/13/2023 | No Access for Inspection | JOHN HAYES |
| HVAC-Final | 2/13/2023 | No Access for Inspection | JOHN HAYES |
| PLUMBING-Final | 2/13/2023 | No Access for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 2/13/2023 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 2/13/2023 | No Access for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 2/24/2023 | Not Ready for Inspection | JOHN HAYES |
| Final | 2/24/2023 | Corrections Issued | JOHN HAYES |
| Green Building Final | 2/24/2023 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Final | 2/24/2023 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Final | 2/24/2023 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 2/24/2023 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 2/24/2023 | Not Ready for Inspection | JOHN HAYES |
| Final | 3/29/2023 | Corrections Issued | JOHN COLEMAN |
| Green Building Final | 3/29/2023 | Corrections Issued | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 3/29/2023 | SGSOV Not Ready | JOHN COLEMAN |
| Smoke Detectors | 3/29/2023 | Corrections Issued | JOHN COLEMAN |
| ELECTRICAL-Final | 6/8/2023 | No Access for Inspection | JOHN HAYES |
| Final | 6/8/2023 | Corrections Issued | JOHN HAYES |
| Green Building Final | 6/8/2023 | No Access for Inspection | JOHN HAYES |
| HVAC-Final | 6/8/2023 | No Access for Inspection | JOHN HAYES |
| PLUMBING-Final | 6/8/2023 | No Access for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 6/8/2023 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 6/8/2023 | No Access for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 6/20/2023 | No Access for Inspection | JOHN COLEMAN |
| HVAC-Final | 6/20/2023 | No Access for Inspection | JOHN COLEMAN |
| PLUMBING-Final | 6/20/2023 | No Access for Inspection | JOHN COLEMAN |
| Final | 9/6/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Green Building Final | 9/6/2023 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 9/6/2023 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 9/6/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 9/28/2023 | Corrections Issued | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 9/28/2023 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 9/28/2023 | Approved | JOHN HAYES |
| Final | 10/11/2023 | Corrections Issued | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 10/11/2023 | SGSOV Not Ready | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 12/27/2023 | SGSOV Not Ready | JOHN HAYES |
| ELECTRICAL-Final | 12/29/2023 | Approved | CRAIG DAVIS |
| HVAC-Final | 12/29/2023 | Approved | CRAIG DAVIS |
| PLUMBING-Final | 12/29/2023 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Final | 1/9/2024 | Approved | JENNIFER RABUCHIN |
| Final | 1/9/2024 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 1/9/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 1/9/2024 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/9/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 1/9/2024 | Approved | JENNIFER RABUCHIN |