3011 S ST ANDREWS PL 90018

Certificate Information: 3011 S ST ANDREWS PL 90018

Application / Permit
21016-20000-12809
Plan Check / Job No.
B21VN06118
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 22'-2.5" x 5'-6" ADDITION TO AND CONVERT THE (E) 22'-2.5" x 20'-0" DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 6/23/2022
Issuing Office
Valley
Current Status
Issued on 6/23/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/25/2021 APPLICANT
Assigned to Plan Check Engineer 9/3/2021 SARKIS HARABEDIAN
Corrections Issued 9/6/2021 SARKIS HARABEDIAN
Applicant returned to address corrections 2/26/2022 SARKIS HARABEDIAN
Plan Check Approved 6/12/2022 SARKIS HARABEDIAN
Building Plans Picked Up 6/14/2022 APPLICANT
Issued 6/23/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/29/2021 WALLIE JONG
Sewer availability Cleared 9/29/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 10/6/2021 WALLIE JONG
Roof/Waste drainage to street Cleared 3/23/2022 WALLIE JONG
HPOZ Cleared 5/31/2022 DANIEL MATA

Contact Information

Contractor Right Choice Home Remodeling Inc The; Lic. No.: 1066456-B 15315 MAGNOLIA BLVD #429      SHERMAN OAKS, CA 91403

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/18/2022 Not Ready for Inspection SABAS ALONSO
METHANE-Barrier 8/18/2022 Approved SABAS ALONSO
METHANE-Subgrade 8/18/2022 Approved SABAS ALONSO
Underground Mechanical 8/18/2022 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 8/23/2022 Corrections Issued STUART CHAPMAN
Green Building Rough 8/23/2022 Not Ready for Inspection STUART CHAPMAN
METHANE-Rough 8/23/2022 Approved STUART CHAPMAN
Grounding or Bonding 8/26/2022 Corrections Issued STUART CHAPMAN
BUILDING-Rough-Frame 10/4/2022 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 10/4/2022 Not Ready for Inspection SABAS ALONSO
Final 10/4/2022 Not Ready for Inspection SABAS ALONSO
Footing/Foundation/Slab 10/4/2022 Not Ready for Inspection SABAS ALONSO
Green Building Final 10/4/2022 Not Ready for Inspection SABAS ALONSO
Green Building Rough 10/4/2022 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 10/4/2022 Not Ready for Inspection SABAS ALONSO
Rough-Elec/Plmb/HVAC 10/4/2022 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 10/4/2022 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 10/4/2022 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 10/11/2022 Corrections Issued STUART CHAPMAN
Green Building Rough 10/11/2022 Not Ready for Inspection STUART CHAPMAN
Rough-Elec/Plmb/HVAC 10/11/2022 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 10/18/2022 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 10/18/2022 Not Ready for Inspection SABAS ALONSO
Rough-Elec/Plmb/HVAC 10/18/2022 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 10/27/2022 Partial Approval SABAS ALONSO
Rough-Elec/Plmb/HVAC 10/27/2022 Approved SABAS ALONSO
BUILDING-Rough-Frame 11/9/2022 Not Ready for Inspection SABAS ALONSO
Green Building Rough 11/9/2022 Approved SABAS ALONSO
Interior/Exterior Lathing 11/21/2022 Partial Approval SABAS ALONSO
Insulation 12/6/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 1/4/2023 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 1/24/2023 Approved SABAS ALONSO
Insulation 1/26/2023 Approved ENRIQUE MIRELES
Drywall Nailing 1/31/2023 Approved ALEJANDRO DE ARTOLA
Shower Pan 2/8/2023 Partial Approval SABAS ALONSO
Shower Pan 2/10/2023 Approved DONALD CRICHLOW