9311-9313 S HOLMES AVE 90002
Certificate Information: 9311-9313 S HOLMES AVE 90002
- Application / Permit
- 21016-20000-12746
- Plan Check / Job No.
- B21VN06077
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) 482 SQ. FT. SFD INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) FOR CONVERSION OF PORTION OF EXISTING SFD ONLY.
- Permit Issued
- Issued on 9/9/2021
- Issuing Office
- Current Status
- CofO Issued on 6/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2021 | JESSE ARELLANO |
| Corrections Issued | 5/29/2021 | JESSE ARELLANO |
| Issued | 9/9/2021 | APPLICANT |
| Building Plans Picked Up | 9/9/2021 | APPLICANT |
| CofO in Progress | 5/16/2022 | ALIZAH MAYAGOITIA |
| CofO Issued | 6/3/2022 | DEROLD HAUFF |
| Permit Finaled | 6/3/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/14/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 6/30/2021 | CELINA MORENO |
| Sewer availability | Cleared | 7/14/2021 | RENZ SORIANO |
| Tenant Habitability Plan | Cleared | 9/3/2021 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/7/2021 | Partial Approval | JOHN KLARIN |
| PLUMBING-Rough | 12/9/2021 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 12/17/2021 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 1/28/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Insulation | 1/28/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 1/28/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Drywall Nailing | 2/11/2022 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 2/11/2022 | Approved | JOHN KLARIN |
| Shower Pan | 2/25/2022 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 3/11/2022 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 4/28/2022 | Approved | JOHN KLARIN |
| Final | 4/28/2022 | Corrections Issued | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 4/28/2022 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 4/28/2022 | Approved | JOHN KLARIN |
| Final | 5/6/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 5/12/2022 | Conditional Approval | ALIZAH MAYAGOITIA |
| Final | 5/16/2022 | OK to Issue CofO | ALIZAH MAYAGOITIA |