7817-7819 N SEDAN AVE 91304

Certificate Information: 7817-7819 N SEDAN AVE 91304

Application / Permit
21016-20000-12697
Plan Check / Job No.
B21VN06055
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan ADU conversion. CONVERT EXISTING ATTACHED GARAGE TO AN ADU PER STATE AND GCS 65852.2(e)(1)(A). ALL WORK PER WOOD FRAME DESIGN.
Permit Issued
Issued on 8/13/2021
Issuing Office
Current Status
CofO Issued on 12/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/15/2021 APPLICANT
Assigned to Plan Check Engineer 5/19/2021 ZAW HAN
Corrections Issued 5/19/2021 ZAW HAN
Building Plans Picked Up 7/13/2021 APPLICANT
Plan Check Approved 8/3/2021 ZAW HAN
Issued 8/13/2021 APPLICANT
CofO in Progress 11/29/2021 VINCENT HANLEY
Permit Finaled 12/1/2021 JOHN JANSON
CofO Issued 12/1/2021 JOHN JANSON
Permit Finaled 12/1/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/20/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 5/21/2021 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 5/21/2021 ADRIAN CASTRO
Sewer availability Cleared 5/21/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/17/2021 Approved HENRY KIM
Footing/Foundation/Slab 8/27/2021 Corrections Issued DAVID STEPANYAN
PLUMBING-Rough 8/27/2021 Corrections Issued DAVID STEPANYAN
Pre-Inspection 8/27/2021 Partial Inspection DAVID STEPANYAN
Footing/Foundation/Slab 8/30/2021 Not Ready for Inspection DAVID STEPANYAN
PLUMBING-Rough 8/30/2021 Partial Approval DAVID STEPANYAN
Sewer 8/30/2021 Approved DAVID STEPANYAN
Footing/Foundation/Slab 9/1/2021 Approved HENRY KIM
ELECTRICAL-Rough 9/20/2021 Corrections Issued DAVID STEPANYAN
Wood Frame 9/20/2021 Not Ready for Inspection DAVID STEPANYAN
ELECTRICAL-Rough 9/30/2021 Partial Approval DAVID STEPANYAN
PLUMBING-Rough 9/30/2021 Approved DAVID STEPANYAN
ELECTRICAL-Rough 10/7/2021 Approved DAVID STEPANYAN
HVAC-Rough 10/7/2021 Partial Approval DAVID STEPANYAN
Interior/Exterior Lathing 10/7/2021 Not Ready for Inspection DAVID STEPANYAN
Pre-Inspection 10/7/2021 Not Ready for Inspection DAVID STEPANYAN
Interior/Exterior Lathing 10/12/2021 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 10/14/2021 Not Ready for Inspection HENRY KIM
HVAC-Rough 10/14/2021 Partial Approval HENRY KIM
Insulation 10/14/2021 Corrections Issued HENRY KIM
Interior/Exterior Lathing 10/14/2021 Not Ready for Inspection HENRY KIM
BUILDING-Rough-Frame 10/27/2021 Approved DAVID STEPANYAN
Drywall Nailing 10/27/2021 Partial Approval DAVID STEPANYAN
Green Building Rough 10/27/2021 Approved DAVID STEPANYAN
HVAC-Rough 10/27/2021 Approved DAVID STEPANYAN
Insulation 10/27/2021 Approved DAVID STEPANYAN
Drywall Nailing 11/1/2021 Approved JESUS PINEDA
Shower Pan 11/1/2021 Approved JESUS PINEDA
Interior/Exterior Lathing 11/4/2021 Approved JESUS PINEDA
Special/Order Compliance 11/8/2021 Approved JESUS PINEDA
ELECTRICAL-Final 11/22/2021 Corrections Issued DAVID STEPANYAN
Final 11/22/2021 Not Ready for Inspection DAVID STEPANYAN
Gas Test 11/22/2021 Not Ready for Inspection DAVID STEPANYAN
Green Building Final 11/22/2021 Corrections Issued DAVID STEPANYAN
HVAC-Final 11/22/2021 Corrections Issued DAVID STEPANYAN
PLUMBING-Final 11/22/2021 Corrections Issued DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 11/22/2021 SGSOV Approved DAVID STEPANYAN
Smoke Detectors 11/22/2021 Approved DAVID STEPANYAN
ELECTRICAL-Final 11/29/2021 Approved VINCENT HANLEY
Final 11/29/2021 OK to Issue CofO VINCENT HANLEY
Gas Test 11/29/2021 Approved VINCENT HANLEY
Green Building Final 11/29/2021 Approved VINCENT HANLEY
HVAC-Final 11/29/2021 Approved VINCENT HANLEY
PLUMBING-Final 11/29/2021 Approved VINCENT HANLEY