17120 W TRIBUNE ST 91344
Certificate Information: 17120 W TRIBUNE ST 91344
- Application / Permit
- 21016-20000-12659
- Plan Check / Job No.
- B21VN06038
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePLAN CHECK* CONVERSION OF (E) GARAGE TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)-(d). WORK PER IB/P/BC 2020-004 WOOD FRAME PRESCRIPTIVE PROVISIONS
- Permit Issued
- Issued on 8/31/2021
- Issuing Office
- Current Status
- CofO Issued on 4/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2021 | LAMAR DAVIS |
| Corrections Issued | 5/20/2021 | LAMAR DAVIS |
| Plan Check Approved | 6/3/2021 | LAMAR DAVIS |
| Issued | 8/31/2021 | APPLICANT |
| CofO in Progress | 4/11/2022 | DAVID SCANTLIN |
| Permit Finaled | 4/19/2022 | JOHN JANSON |
| CofO Issued | 4/19/2022 | JOHN JANSON |
| Permit Finaled | 4/19/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/21/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 5/21/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 5/21/2021 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 5/21/2021 | LEE GUILBEAUX |
Contact Information
| Contractor | M D H Builders / Design / Development; Lic. No.: 1067773-B | 6700 FALLBROOK AVE STE 100 WEST HILLS, CA 91307 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/29/2021 | Approved | TROY SANDERS |
| Deputy Drilled-In Anchors | 9/30/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 10/8/2021 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Rough | 11/12/2021 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 11/12/2021 | Approved | DAVID SCANTLIN |
| Wood Frame | 11/18/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Insulation | 11/24/2021 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 11/24/2021 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 12/2/2021 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 12/2/2021 | Approved | DAVID SCANTLIN |
| Final | 2/15/2022 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 2/15/2022 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 2/15/2022 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 2/15/2022 | Approved | DAVID SCANTLIN |
| Final | 4/8/2022 | OK to Issue CofO | DAVID SCANTLIN |