4937 N DENNY AVE 91601
Certificate Information: 4937 N DENNY AVE 91601
- Application / Permit
- 21016-20000-12390
- Plan Check / Job No.
- B21VN05908
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) DETACHED 417 SQ. FT. GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 6/3/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/14/2021 | OMAR GARNICA |
| Corrections Issued | 5/14/2021 | OMAR GARNICA |
| Plan Check Approved | 6/7/2021 | OMAR GARNICA |
| Building Plans Picked Up | 7/2/2021 | APPLICANT |
| Issued | 6/3/2022 | APPLICANT |
| CofO in Progress | 12/28/2022 | JOHN HAYES |
| CofO Issued | 4/26/2023 | MICHAEL SMITH |
| Permit Finaled | 4/26/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/20/2021 | CARLOS AGUILERA |
| Hold | Cleared | 5/20/2021 | JASON SHEETS |
| Roof/Waste drainage to street | Cleared | 5/20/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/20/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | S & L Construction; Lic. No.: 503799-B | 5826 BURTON AVE SAN GABRIEL, CA 91775 |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/14/2022 | No Access for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 6/22/2022 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 6/29/2022 | Partial Approval | JOHN HAYES |
| Footing/Foundation/Slab | 7/8/2022 | Approved | JOHN HAYES |
| Underground Mechanical | 7/8/2022 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 7/14/2022 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 7/28/2022 | Corrections Issued | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2022 | Corrections Issued | ALAN MORELOS |
| Green Building Rough | 7/28/2022 | Not Ready for Inspection | ALAN MORELOS |
| Wood Frame | 7/28/2022 | Not Ready for Inspection | ALAN MORELOS |
| ELECTRICAL-Rough | 8/3/2022 | Not Ready for Inspection | ALAN MORELOS |
| PLUMBING-Rough | 8/3/2022 | Approved | ALAN MORELOS |
| Wood Frame | 8/3/2022 | Corrections Issued | ALAN MORELOS |
| ELECTRICAL-Rough | 8/10/2022 | Partial Approval | JOHN HAYES |
| Interior/Exterior Lathing | 8/10/2022 | Partial Approval | JOHN HAYES |
| Insulation | 8/16/2022 | Partial Approval | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2022 | Approved | ALAN MORELOS |
| HVAC-Rough | 8/23/2022 | Not Ready for Inspection | ALAN MORELOS |
| Insulation | 8/23/2022 | Approved | ALAN MORELOS |
| HVAC-Rough | 8/29/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 9/6/2022 | Approved | JOHN HAYES |
| Special/Order Compliance | 9/6/2022 | Corrections Issued | JOHN HAYES |
| Gas Test | 9/16/2022 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 10/27/2022 | Not Ready for Inspection | JOHN HAYES |
| Drywall Nailing | 10/27/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 10/27/2022 | Corrections Issued | JOHN HAYES |
| Green Building Final | 10/27/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 10/27/2022 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 10/27/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 11/4/2022 | Not Ready for Inspection | JOHN HAYES |
| Drywall Nailing | 11/4/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 11/4/2022 | Corrections Issued | JOHN HAYES |
| Green Building Final | 11/4/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 11/4/2022 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 11/4/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 12/28/2022 | Approved | JOHN HAYES |
| Drywall Nailing | 12/28/2022 | Approved | JOHN HAYES |
| Final | 12/28/2022 | OK to Issue CofO | JOHN HAYES |
| Green Building Final | 12/28/2022 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 12/28/2022 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 12/28/2022 | Approved | JOHN HAYES |