5402 N SHIRLEY AVE 91356

Certificate Information: 5402 N SHIRLEY AVE 91356

Application / Permit
21016-20000-12131
Plan Check / Job No.
B21VN05772
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**ePlan new detached adu
Permit Issued
Issued on 4/19/2023
Issuing Office
Current Status
Issued on 4/19/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/15/2021 APPLICANT
Assigned to Plan Check Engineer 6/24/2021 ARSALAN SHABESTARI
Corrections Issued 7/2/2021 ARSALAN SHABESTARI
Quality Review Completed 7/15/2021 MICHAEL PEREZ
Applicant returned to address corrections 11/22/2021 ARSALAN SHABESTARI
Applicant returned to address corrections 2/14/2022 ARSALAN SHABESTARI
Plan Check Approved 4/19/2023 ARSALAN SHABESTARI
Issued 4/19/2023 APPLICANT

Permit Application Clearance Information

Low Impact Development Cleared 4/27/2022 ANDRES COVARRUBIAS
Address approval Cleared 6/23/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 6/23/2022 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 6/23/2022 MEGAN GODINEZ
Sewer availability Cleared 6/23/2022 MEGAN GODINEZ
Hydrant and Access approval Cleared 7/6/2022 ROBERT DUFF
Grading Pre-Inspection Cleared 7/7/2022 ROBERT HUGHES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/2/2023 Approved SEAN HAUPT
Footing/Foundation/Slab 5/9/2023 Corrections Issued SEAN HAUPT
Footing/Foundation/Slab 5/15/2023 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 6/27/2023 Approved SEAN HAUPT
Green Building Rough 6/27/2023 Not Ready for Inspection SEAN HAUPT
Verify Sprinkler Sign Off 6/27/2023 Not Ready for Inspection SEAN HAUPT
Insulation 6/30/2023 Partial Approval SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 9/28/2023 Not Ready for Inspection SEAN HAUPT
HVAC-Rough 11/29/2023 Approved SEAN HAUPT
PLUMBING-Rough 11/29/2023 Corrections Issued SEAN HAUPT
ELECTRICAL-Rough 1/3/2024 No Access for Inspection JEFFREY PARD
PLUMBING-Rough 1/3/2024 No Access for Inspection JEFFREY PARD
ELECTRICAL-Rough 1/9/2024 Approved SEAN HAUPT
PLUMBING-Rough 1/9/2024 Approved SEAN HAUPT
Shower Pan 1/9/2024 Approved SEAN HAUPT
BUILDING-Rough-Frame 1/16/2024 Not Ready for Inspection SEAN HAUPT
Deputy Reinf. Concrete 1/16/2024 Approved SEAN HAUPT
Green Building Rough 1/16/2024 Not Ready for Inspection SEAN HAUPT
HVAC-Rough 1/16/2024 Not Ready for Inspection SEAN HAUPT
Interior/Exterior Lathing 1/16/2024 Not Ready for Inspection SEAN HAUPT
Verify Sprinkler Sign Off 1/16/2024 Approved SEAN HAUPT
BUILDING-Rough-Frame 2/14/2024 Approved JOHN KIDWELL
Green Building Rough 2/14/2024 Approved JOHN KIDWELL
Interior/Exterior Lathing 2/14/2024 Partial Approval JOHN KIDWELL
Verify Sprinkler Sign Off 2/14/2024 Approved JOHN KIDWELL
Insulation 2/16/2024 Approved JOHN KIDWELL
Drywall Nailing 3/12/2024 Approved JOHN KIDWELL
PLUMBING-Rough 3/12/2024 Partial Approval JOHN KIDWELL
PLUMBING-Rough 5/14/2025 Partial Approval JOHN KIDWELL
Final 8/12/2025 Not Ready for Inspection JOHN KIDWELL
Green Building Final 8/12/2025 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 8/12/2025 SGSOV Not Ready JOHN KIDWELL
Service/Power Release 8/12/2025 Not Ready for Inspection JOHN KIDWELL
Smoke Detectors 8/12/2025 Not Ready for Inspection JOHN KIDWELL
Final 12/18/2025 Not Ready for Inspection JOHN KIDWELL
Green Building Final 12/18/2025 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 12/18/2025 SGSOV Not Ready JOHN KIDWELL
Service/Power Release 12/18/2025 Not Ready for Inspection JOHN KIDWELL
Smoke Detectors 12/18/2025 Approved JOHN KIDWELL