5256 N BEEMAN AVE 91607

Certificate Information: 5256 N BEEMAN AVE 91607

Application / Permit
21016-20000-11994
Plan Check / Job No.
B21VN05719
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan ADU conversion. CONVERTING THE EXISTING GARAGE TO AN ADU PER GCS 65852.2(e)(1)(A) AND PER WFPP
Permit Issued
Issued on 6/21/2021
Issuing Office
Current Status
CofO Issued on 4/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/11/2021 APPLICANT
Assigned to Plan Check Engineer 5/13/2021 CRYSTEL MAALOUF
Corrections Issued 5/13/2021 CRYSTEL MAALOUF
Plan Check Approved 6/14/2021 CRYSTEL MAALOUF
Issued 6/21/2021 APPLICANT
CofO in Progress 3/18/2022 JACK KARGODORIAN
CofO Issued 4/5/2022 MICHAEL SMITH
Permit Finaled 4/5/2022 MICHAEL SMITH

Permit Application Clearance Information

Sewer availability Cleared 5/21/2021 GABRIEL ROBLES
Address approval Cleared 5/24/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 5/25/2021 GABRIEL ROBLES
Construction near power lines Cleared 6/4/2021 WALTER RAMIREZ
ZI Cleared 6/7/2021 CORREY KITCHENS
ZI Cleared 6/7/2021 CORREY KITCHENS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/12/2021 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 11/12/2021 Partial Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 11/24/2021 Partial Approval CHRISTOPHE COCHRAN
ELECTRICAL-Rough 11/24/2021 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 11/24/2021 Approved CHRISTOPHE COCHRAN
Sewer 11/24/2021 Approved CHRISTOPHE COCHRAN
Underground Mechanical 11/24/2021 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 12/9/2021 Partial Approval ASHLEY THOMPSON
Insulation 12/9/2021 Partial Approval ASHLEY THOMPSON
Interior/Exterior Lathing 12/9/2021 Not Ready for Inspection ASHLEY THOMPSON
BUILDING-Rough-Frame 12/13/2021 Corrections Issued CHRISTOPHE COCHRAN
Interior/Exterior Lathing 12/13/2021 Partial Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 12/16/2021 Approved JACK KARGODORIAN
Drywall Nailing 12/28/2021 Corrections Issued ASHLEY THOMPSON
Interior/Exterior Lathing 12/28/2021 Approved ASHLEY THOMPSON
Drywall Nailing 12/29/2021 Approved CHRISTOPHE COCHRAN
Final 1/25/2022 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 1/25/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 1/25/2022 SGSOV Not Ready CHRISTOPHE COCHRAN
Smoke Detectors 1/25/2022 Approved CHRISTOPHE COCHRAN
Final 1/28/2022 Corrections Issued JENNIFER RABUCHIN
Green Building Final 1/28/2022 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 1/28/2022 SGSOV Not Ready JENNIFER RABUCHIN
Final 2/11/2022 Corrections Issued JACK KARGODORIAN
Green Building Final 2/11/2022 Not Ready for Inspection JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 2/11/2022 SGSOV Gas Company JACK KARGODORIAN
Final 2/22/2022 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 2/22/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 3/18/2022 OK to Issue CofO JACK KARGODORIAN
Green Building Final 3/18/2022 Approved JACK KARGODORIAN