7648 N AMESTOY AVE 91406

Certificate Information: 7648 N AMESTOY AVE 91406

Application / Permit
21016-20000-11920
Plan Check / Job No.
B21VN05668
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18'-2" X 20'-2" DETACHED GARAGE AND 20' X 25'-2" STORAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP.
Permit Issued
Issued on 6/14/2021
Issuing Office
Current Status
CofO Issued on 8/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/7/2021 APPLICANT
Assigned to Plan Check Engineer 5/14/2021 RAPHAEL ROSAS
Corrections Issued 5/15/2021 RAPHAEL ROSAS
Applicant returned to address corrections 6/7/2021 RAPHAEL ROSAS
Issued 6/14/2021 APPLICANT
Building Plans Picked Up 6/15/2021 APPLICANT
CofO in Progress 8/6/2021 JACK KARGODORIAN
CofO Issued 8/23/2021 MICHAEL SMITH
Permit Finaled 8/23/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/19/2021 LEE GUILBEAUX
Sewer availability Cleared 5/19/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 5/20/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 5/20/2021 LEE GUILBEAUX
Construction near power lines Cleared 6/7/2021 JOHN BACON

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/18/2021 Approved JACK KARGODORIAN
HVAC-Rough 6/18/2021 Approved JACK KARGODORIAN
PLUMBING-Rough 6/18/2021 Approved JACK KARGODORIAN
Underground Mechanical 6/18/2021 Approved JACK KARGODORIAN
Gas Test 6/22/2021 Approved JACK KARGODORIAN
Insulation 6/24/2021 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 6/24/2021 Approved JAVIER RAMOS JR
Shower Pan 6/24/2021 Approved JAVIER RAMOS JR
Drywall Nailing 6/29/2021 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 7/29/2021 Not Ready for Inspection DAVID SCANTLIN
Final 7/29/2021 Not Ready for Inspection DAVID SCANTLIN
Green Building Final 7/29/2021 Not Ready for Inspection DAVID SCANTLIN
Green Building Rough 7/29/2021 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 7/29/2021 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 7/29/2021 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 8/6/2021 Approved JACK KARGODORIAN
ELECTRICAL-Final 8/6/2021 Approved JACK KARGODORIAN
Final 8/6/2021 OK to Issue CofO JACK KARGODORIAN
Green Building Final 8/6/2021 Approved JACK KARGODORIAN
HVAC-Final 8/6/2021 Approved JACK KARGODORIAN
PLUMBING-Final 8/6/2021 Approved JACK KARGODORIAN