6154-6156 N AURA AVE 91335

Certificate Information: 6154-6156 N AURA AVE 91335

Application / Permit
21016-20000-11797
Plan Check / Job No.
B21VN05614
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 20' X 20'-4" ATTACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 6/3/2021
Issuing Office
Current Status
CofO Issued on 11/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/10/2021 APPLICANT
Assigned to Plan Check Engineer 5/14/2021 RAPHAEL ROSAS
Corrections Issued 5/15/2021 RAPHAEL ROSAS
Issued 6/3/2021 APPLICANT
Building Plans Picked Up 6/7/2021 APPLICANT
CofO in Progress 11/1/2021 STEVEN BACK
CofO Issued 11/2/2021 JOHN JANSON
Permit Finaled 11/2/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/24/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/24/2021 CARLOS AGUILERA
Sewer availability Cleared 5/24/2021 CARLOS AGUILERA
ZI Cleared 5/24/2021 LAUREN PADICK

Contact Information

Contractor Owner-Builder       ,
Engineer Hajdari,, Genti; Lic. No.: C88031 140 S MENTOR AVE APT #207      PASADENA, CA 91106

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 7/9/2021 Corrections Issued HENRY KIM
Deputy Drilled-In Anchors 7/9/2021 Approved HENRY KIM
Footing/Foundation/Slab 7/9/2021 Corrections Issued HENRY KIM
Deputy Drilled-In Anchors 7/22/2021 Conditional Approval RYAN SALAZAR
BUILDING-Rough-Frame 7/26/2021 Partial Inspection HENRY KIM
Footing/Foundation/Slab 7/26/2021 Approved HENRY KIM
PLUMBING-Rough 7/26/2021 Corrections Issued HENRY KIM
Sewer 7/26/2021 Corrections Issued HENRY KIM
Gas Test 7/28/2021 Approved PETER FOLLING
PLUMBING-Rough 7/28/2021 Not Ready for Inspection PETER FOLLING
Sewer 7/28/2021 Approved PETER FOLLING
PLUMBING-Rough 7/30/2021 Corrections Issued HENRY KIM
PLUMBING-Rough 8/3/2021 Partial Approval HENRY KIM
BUILDING-Rough-Frame 8/6/2021 Not Ready for Inspection HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 8/10/2021 Corrections Issued HENRY KIM
BUILDING-Rough-Frame 8/17/2021 Not Ready for Inspection HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 8/17/2021 Partial Approval HENRY KIM
ELECTRICAL-Rough 8/25/2021 Approved HENRY KIM
Gas Test 8/25/2021 Corrections Issued HENRY KIM
PLUMBING-Rough 8/25/2021 Corrections Issued HENRY KIM
Insulation 8/30/2021 Partial Approval HENRY KIM
Rough-Elec/Plmb/HVAC 8/30/2021 Approved HENRY KIM
ELECTRICAL-Final 9/2/2021 Corrections Issued HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 9/2/2021 Approved HENRY KIM
Insulation 9/2/2021 Corrections Issued HENRY KIM
Shower Pan 9/2/2021 Approved HENRY KIM
Drywall Nailing 9/10/2021 Approved RYAN SALAZAR
Insulation 9/10/2021 Approved RYAN SALAZAR
Interior/Exterior Lathing 9/10/2021 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 10/26/2021 Approved STEVEN BACK
Final 10/26/2021 Corrections Issued STEVEN BACK
Green Building Final 10/26/2021 Approved STEVEN BACK
Green Building Rough 10/26/2021 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 10/26/2021 SGSOV Not Ready STEVEN BACK
Smoke Detectors 10/26/2021 Approved STEVEN BACK
ELECTRICAL-Final 11/1/2021 Approved STEVEN BACK
Final 11/1/2021 OK to Issue CofO STEVEN BACK
HVAC-Final 11/1/2021 Approved STEVEN BACK
PLUMBING-Final 11/1/2021 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 11/1/2021 SGSOV Approved STEVEN BACK
Service/Power Release 11/1/2021 Approved STEVEN BACK