17177 W SIMONDS ST 91344
Certificate Information: 17177 W SIMONDS ST 91344
- Application / Permit
- 21016-20000-11413
- Plan Check / Job No.
- B21VN05442
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 9/9/2021
- Issuing Office
- Current Status
- Issued on 9/9/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/7/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 5/8/2021 | JEROME MAGAT PALMA |
| Issued | 9/9/2021 | APPLICANT |
| Building Plans Picked Up | 9/10/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/17/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 5/17/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/17/2021 | GABRIEL ROBLES |
| Grading Pre-Inspection | Cleared | 7/1/2021 | TIMOTHY POWELL |
| Construction near power lines | Cleared | 8/31/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia, Zelada, Eddy Alexander; Lic. No.: S6159 | 17958 LULL ST RESEDA, CA 91335 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/29/2021 | Partial Approval | DAVID SCANTLIN |
| Footing/Foundation/Slab | 12/29/2021 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 12/29/2021 | Partial Approval | DAVID SCANTLIN |
| ELECTRICAL-Rough | 1/12/2022 | Corrections Issued | STEVEN BACK |
| HVAC-Rough | 1/12/2022 | Not Ready for Inspection | STEVEN BACK |
| Insulation | 1/12/2022 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 1/12/2022 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 1/14/2022 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2022 | Partial Approval | SEAN WIRCH |
| PLUMBING-Rough | 1/14/2022 | Approved | SEAN WIRCH |
| Deputy Drilled-In Anchors | 1/19/2022 | Conditional Approval | DAVID SCANTLIN |
| HVAC-Rough | 1/21/2022 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 1/21/2022 | Partial Approval | DAVID SCANTLIN |
| Insulation | 1/31/2022 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 2/7/2022 | Approved | DAVID SCANTLIN |
| Green Building Rough | 2/7/2022 | Approved | DAVID SCANTLIN |
| MERV13>=Rough | 2/7/2022 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 2/11/2022 | Approved | DAVID SCANTLIN |
| Final | 3/11/2022 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 3/11/2022 | Approved | DAVID SCANTLIN |
| MERV13>=Final | 3/11/2022 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 3/11/2022 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 3/11/2022 | Approved | DAVID SCANTLIN |