1768 3/4 W 37TH DR 90018
Certificate Information: 1768 3/4 W 37TH DR 90018
- Application / Permit
- 21016-20000-11346
- Plan Check / Job No.
- B21VN05410
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DET. GARAGE TO ADU (18'-3"x20'-0"), 327 SQFT PER LAMC 12.22 A.33(c)(d)
- Permit Issued
- Issued on 1/11/2022
- Issuing Office
- Current Status
- CofO Issued on 8/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2021 | PETER MOSESIAN |
| Corrections Issued | 6/6/2021 | PETER MOSESIAN |
| Quality Review Completed | 6/11/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 6/18/2021 | APPLICANT |
| Plan Check Approved | 11/12/2021 | PETER MOSESIAN |
| Issued | 1/11/2022 | APPLICANT |
| CofO in Progress | 8/11/2023 | SABAS ALONSO |
| Permit Finaled | 8/13/2023 | DEROLD HAUFF |
| CofO Issued | 8/13/2023 | DEROLD HAUFF |
| Permit Finaled | 8/13/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/18/2021 | WALLIE JONG |
| Sewer availability | Cleared | 8/18/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/27/2021 | WALLIE JONG |
| Community Plan Implem. Overlay | Cleared | 9/28/2021 | PABLO ESTRADA |
Contact Information
| Contractor | Samama Albert; Lic. No.: 557517-B | 22487 LIBERTY BELL RD CALABASAS, CA 91302 |
| Engineer | Samama,, Albert; Lic. No.: C43288 | 22487 LIBERTY BELL RD CALABASAS, CA 91302 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 8/17/2022 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 8/17/2022 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 8/29/2022 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 9/13/2022 | Not Ready for Inspection | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 9/16/2022 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 9/16/2022 | Partial Approval | SABAS ALONSO |
| Piling/Pier/Caisson | 9/16/2022 | Not Ready for Inspection | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 10/3/2022 | Approved | HORACE FULTZ |
| Footing/Foundation/Slab | 10/3/2022 | Approved | HORACE FULTZ |
| BUILDING-Rough-Frame | 10/18/2022 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2022 | Partial Approval | SABAS ALONSO |
| Green Building Rough | 10/18/2022 | Not Ready for Inspection | SABAS ALONSO |
| Wood Frame | 10/18/2022 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 12/7/2022 | Approved | SABAS ALONSO |
| HVAC-Rough | 12/7/2022 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Final | 12/7/2022 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 12/7/2022 | Corrections Issued | SABAS ALONSO |
| Shower Pan | 12/7/2022 | Not Ready for Inspection | SABAS ALONSO |
| Wood Frame | 12/7/2022 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 12/12/2022 | Approved | LILIANA PORTILLO |
| Shower Pan | 12/12/2022 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 12/14/2022 | Conditional Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 12/14/2022 | Approved | SABAS ALONSO |
| HVAC-Rough | 12/14/2022 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 12/14/2022 | Partial Approval | SABAS ALONSO |
| PLUMBING-Rough | 12/14/2022 | Approved | SABAS ALONSO |
| Insulation | 12/20/2022 | Approved | SABAS ALONSO |
| Drywall Nailing | 12/27/2022 | Approved | SABAS ALONSO |
| Green Building Rough | 12/27/2022 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 1/5/2023 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 3/8/2023 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 3/8/2023 | Corrections Issued | SABAS ALONSO |
| Final | 3/8/2023 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 3/8/2023 | Corrections Issued | SABAS ALONSO |
| HVAC-Final | 3/8/2023 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Final | 3/8/2023 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 3/8/2023 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 3/8/2023 | Approved | SABAS ALONSO |
| Final | 4/14/2023 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Final | 4/14/2023 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 4/14/2023 | SGSOV Not Ready | SABAS ALONSO |
| Final | 5/4/2023 | No Access for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 5/4/2023 | SGSOV Not Ready | SABAS ALONSO |
| Final | 7/13/2023 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 7/13/2023 | SGSOV Approved | SABAS ALONSO |
| Final | 8/10/2023 | OK to Issue CofO | SABAS ALONSO |